πŸ“£ Report Something
Proposed

Digital Realty data center at 725 E. Trade St.

Digital Realty plans a four-story, 12-megawatt data center in uptown Charlotte. It was already in the works before the city's pause on new data centers.

πŸ‘₯ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: In development before Charlotte's June 2026 pause, so it may continue.

πŸ•’ Latest update (June 8, 2026): Charlotte paused new data center projects for 150 days; this project was already in the pipeline and may continue.

What we know

  • πŸ“ Where725 E. Trade St., uptown Charlotte, Charlotte, Mecklenburg County
  • 🏒 CompanyDigital Realty
  • ⚑ Power it needs12 megawatts (about as much as 9,600 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • June 8, 2026
    Charlotte paused new data center projects for 150 days; this project was already in the pipeline and may continue.

Local votes and rules

⏸️ Pause on new data centers

Charlotte City Council unanimously paused new data center applications for 150 days, until Nov. 5, 2026 or until new rules pass. A consultant and city team will study effects and propose rules. Projects already approved or in permitting can continue.

June 8, 2026

πŸ—ΊοΈ Zoning change

Charlotte City Council approved rezoning 156 acres off Moores Chapel Road for a Digital Realty data center campus of up to about 3 million square feet. Because it was approved first, the 2026 city pause does not apply to it.

May 2025
πŸ›°οΈ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. What Charlotte wants to learn during its 150-day moratorium on new data centers Β· Bisnow Β· July 22, 2026
  2. Charlotte slams the brakes on data centers as neighborhood battle heats up Β· Hoodline Β· July 23, 2026

See something wrong? Tell us and we'll fix it.