Approved, not built yet

Digital Realty data center campus on Moores Chapel Road

Also called: Digital Realty Charlotte campus

Digital Realty plans one of North Carolina's largest data centers, up to 3 million square feet on 156 acres in west Charlotte. The city approved the rezoning in 2025. A new Duke Energy substation will serve it.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: City Council approved the rezoning in May 2025. Trees have been cleared; Duke Energy plans a new substation paid for by the developer.

πŸ•’ Latest update (Aug 2026): Duke Energy plans for a new substation for the site were reported.

What we know

  • πŸ“ Where12899 Moores Chapel Road, between I-85 and Wilkinson Boulevard, west Charlotte near the airport, Charlotte, Mecklenburg County
  • 🏒 CompanyDigital Realty
  • 🌳 Size156 acres
  • πŸ”Œ Where the power comes fromDuke Energy; a new substation will be built near the airport. The developer pays its cost.
  • πŸ—Ό New power linesYes

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • May 2025
    Charlotte City Council approved rezoning 156 acres for a data center of up to 3 million square feet.
  • Aug 2026
    Duke Energy plans for a new substation for the site were reported.

Local votes and rules

⏸️ Pause on new data centers

Charlotte City Council unanimously paused new data center applications for 150 days, until Nov. 5, 2026 or until new rules pass. A consultant and city team will study effects and propose rules. Projects already approved or in permitting can continue.

June 8, 2026

πŸ—ΊοΈ Zoning change

Charlotte City Council approved rezoning 156 acres off Moores Chapel Road for a Digital Realty data center campus of up to about 3 million square feet. Because it was approved first, the 2026 city pause does not apply to it.

May 2025
πŸ›°οΈ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. North Carolina's largest data center is going up in west Charlotte Β· Charlotte Observer (via Yahoo) Β· Oct 21, 2025
  2. Multimillion-dollar power substation planned near Charlotte airport Β· WSOC-TV Β· Aug 14, 2026
  3. Charlotte considers rezoning for biggest data center in N.C. Β· GovTech Β· 2025