2 data center projects in Rosemount City
Who decides here: the City Council of Rosemount City votes on zoning. The Dakota County may review big projects too.
In Rosemount City
Meta Rosemount data center
Rosemount, Dakota County
280 acres · for Meta
🕒 March 14, 2024: Meta and Gov. Walz announced an $800 million, 715,000 square foot data center in Rosemou…
ProposedDakota East Area site in Rosemount (Tract technology park plan)
Rosemount, Dakota County
447 acres
🕒 July 15, 2025: Rosemount adopted the environmental review (AUAR) as adequate.
Reported in the news, not confirmed yet
Nearby (within 15 miles)
QLevr data center at former Travel Tags site (Inver Grove Heights)
Inver Grove Heights, Dakota County
🕒 Sept 14, 2026: City Council voted 3-1 to exempt the QLevr project from the moratorium, settling the law…
Stopped or cancelledabout 6 miles awayApple Valley Technology Park (Oppidan / Rockport)
Apple Valley, Dakota County
🕒 July 9, 2026: City adopted a one-year pause (moratorium) on new data centers.
Being builtabout 7 miles awayOppidan data center on Argenta Trail (Eagan)
Eagan, Dakota County
🕒 June 2025: Oppidan broke ground on a 61,000 square foot data center, built for one tenant.
Reported in the news, not confirmed yet
Approved, not built yetabout 8 miles awayFarmington Technology Park (Tract data center campus)
Farmington, Dakota County
340 acres
🕒 Sept 16, 2026: Plaintiffs filed dismissals in both lawsuits, according to the city. The residents' grou…
Stopped or cancelledabout 10 miles awayHampton technology park data center idea (Oppidan)
Hampton, Dakota County
🕒 2025: Oppidan paused its Hampton and North Mankato data center plans, citing how long the stat…
Reported in the news, not confirmed yet
Stopped or cancelledabout 10 miles awayLakeville industrial site studied for a data center (Olam Holdings)
Lakeville, Dakota County
152 acres
🕒 May 27, 2026: A judge ruled the review was legal and said the data center talks are inactive.
Local votes and rules
⏸️ Pause on new data centers
Rosemount paused new data center projects for one year. The city wants to study water use, noise and other effects of the Meta data center already being built there.
What you can do
- Get told first.
We'll email you if anything changes in Rosemount City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Rosemount City: Northern States Power Co. - Minnesota (company) or Dakota Electric Association (co-op (owned by its members)) or City of St Paul (not available).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Minnesota.
🙋 Open tasks here
- Is the Rosemount data center running yet?
- How much water does it use per day?
- How many backup diesel generators are on site?
- Is Tract behind the Rosemount Dakota East site, and is a data center planned there?
- Has any land use application been filed for this site?