Send us a tip
Being built

Oppidan data center on Argenta Trail (Eagan)

Oppidan is building a 61,000 square foot data center on Argenta Trail in Eagan for one tenant. It broke ground in June 2025 and was expected to finish in 2026.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Eagan City.

Where things stand: Being built Ground broken in June 2025; expected done in 2026.

❓ 2 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (June 2025): Oppidan broke ground on a 61,000 square foot data center, built for one tenant.

What we know

  • 📍 Where3621 Argenta Trail, just south of the Eagan YMCA (550 Opperman Dr.), Eagan, Dakota County
  • 🏢 CompanyOppidan Investment Co.
  • 🌳 Size14.51 acres
  • ⚡ Power it needs5 megawatts (about as much as 4,000 homes)
  • 🔌 Where the power comes fromDakota Electric Association and Great River Energy are project partners.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the Dakota County parcel record: the developer's company CLOP Eagan MN LLC owns 3621 Argenta Trail, with a building of about 60,700 sq ft first recorded in 2025.

    What happened so far

    • June 2025
      Oppidan broke ground on a 61,000 square foot data center, built for one tenant.

    Local votes and rules

    ⚖️ Court case

    A data center owner, Eagan Capital, sued Eagan over its data center pause. The company says only the state utility commission can regulate power use. It asks for $50,000. Earlier, in May, the city denied the company a permit after cooling units were set up without permits. The city says it will defend the pause.

    June 15, 2026

    ⏸️ Pause on new data centers

    Eagan paused new data centers and crypto mining for one year. It covers sites within 500 feet of homes or that use more than 20 megawatts of power. It was the first data center pause in Minnesota. The vote was unanimous.

    Feb 17, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Oppidan breaks ground on new data center in Minnesota · Institutional Real Estate, Inc. · June 6, 2025
    2. Dakota County tax parcel record(s) 108700301020 · Dakota County GIS · Oct 8, 2026
    3. Oppidan Breaks Ground on 61,000 SF Data Center in Eagan, Minnesota · REBusinessOnline · June 2025
    4. USGS aerial image of the site · USGS The National Map · Oct 8, 2026
    5. Eagan approves plan for 1-year pause on data center projects in the city · KSTP · Feb 2026

    See something wrong? Tell us and we'll fix it.