Lakeville industrial site studied for a data center (Olam Holdings)

Lakeville studied a 152-acre farm site for an industrial park, and the study papers pointed to a possible data center. An environmental group sued. In May 2026 a judge upheld the city's review and noted the data center idea is no longer moving.

✔ ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: The city's data center talks stopped. A judge ruled in May 2026 that the city's environmental review was legal and that the data center idea is inactive.

🕒 Latest update (May 27, 2026): A judge ruled the review was legal and said the data center talks are inactive.

What we know

  • 📍 WhereLakeville, Dakota County
  • 🏢 CompanyOlam Holdings 1 LLC (landowner)
  • 🌳 Size152 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • 2025
    City reviewed an environmental study (AUAR) for an industrial or office park on a 152-acre farm. Study papers hinted at a data center.
  • Aug 2025
    MCEA sued the city over the environmental review.
  • May 27, 2026
    A judge ruled the review was legal and said the data center talks are inactive.

Local votes and rules

⚖️ Court case

A judge ruled that Lakeville's environmental review of the 152-acre Olam site was legal. The Minnesota Center for Environmental Advocacy had argued the city ignored signs of a possible data center.

May 2026
🛰️ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. Court rules environmental review adequate for Lakeville development · Minnesota Center for Environmental Advocacy · May 27, 2026
  2. Judge sides with Lakeville in data center review lawsuit · Minnesota Lawyer · June 1, 2026