No project in St. Charles City, but 6 nearby
Who decides here: the City Council of St. Charles City votes on zoning. The Kane County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Hut 8 data center (1780 Hubbard Ave., Batavia)
Batavia, Kane County
🕒 Sept 2, 2025: City Council approved a water deal 9-2 that caps average use at 1,000 gallons a day and …
Stopped or cancelledabout 5 miles awayWhite Rose Partners data center (Kenyon Road and Route 25, South Elgin)
South Elgin, Kane County
20 acres
🕒 Oct 5, 2026: South Elgin Village Board unanimously approved a 12-month pause on building data centers…
Reported in the news, not confirmed yet
Being builtabout 12 miles awayCompass Datacenters campus at former Sears headquarters (Hoffman Estates)
Hoffman Estates, Cook County
273 acres
🕒 Dec 2025: Village issued permits; walls for the first two data center buildings went up.
Stopped or cancelledabout 13 miles awayPlum Farms rezoning for possible data center (Higgins Road and Route 59)
Hoffman Estates, Cook County
186 acres
🕒 June 30, 2026: Landowner withdrew its rezoning request after more than 3,250 people signed a petition a…
Stopped or cancelledabout 14 miles awayKaris Critical data center at former Lucent campus (Naperville)
Naperville, DuPage County
🕒 Jan 20, 2026: Naperville City Council voted 6-1 to deny the data center after months of debate and a p…
Stopped or cancelledabout 15 miles awayCloud Centers data center at former Lockformer site (711 Ogden Ave., Lisle)
Lisle, DuPage County
18 acres
🕒 March 2026: Developer told the village it withdrew its application.
What you can do
- Get told first.
We'll email you if anything changes in St. Charles City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in St. Charles City: Commonwealth Edison Co. (company) or City of St Charles (run by the town).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Illinois.