Cloud Centers data center at former Lockformer site (711 Ogden Ave., Lisle)

Cloud Centers proposed a two-story, 50-megawatt data center on the old Lockformer factory site on Ogden Avenue. Hundreds of residents turned out against it, and the developer withdrew in March 2026.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled Developer withdrew its application in March 2026, after a packed January hearing had to be postponed.

📣 See work going on anyway? Tell us

Last checked Oct 8, 2026.

🕒 Latest update (March 2026): Developer told the village it withdrew its application.

What we know

  • 📍 Where711 Ogden Ave. (former Lockformer site, about 18 acres), Lisle, DuPage County
  • 🏢 CompanyCloud Centers, LLC
  • 🌳 Size18 acres
  • ⚡ Power it needs50 megawatts (about as much as 40,000 homes)

🔎 What we checked

  • Oct 8, 2026: We checked the site location: the address 711 Ogden Avenue in Lisle was found on the map.

What happened so far

  • Jan 21, 2026
    Planning and zoning hearing was postponed after more than 300 residents packed Village Hall.
  • March 2026
    Developer told the village it withdrew its application.
🛰️ See it from above

Drag the slider to compare the land before and now.

20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. Overflow uproar over Lisle data center plan shuts down hearing · Hoodline · Jan 2026
  2. Lisle data center application withdrawn by developer · Patch (Lisle) · March 12, 2026
  3. Geocode of 711 E Ogden Ave, Lisle · OpenStreetMap Nominatim · Oct 8, 2026

See something wrong? Tell us and we'll fix it.