No project in West Chicago City, but 7 nearby
Who decides here: the City Council of West Chicago City votes on zoning. The DuPage County may review big projects too.
Nearby (within 15 miles)
Hut 8 data center (1780 Hubbard Ave., Batavia)
Batavia, Kane County
π Sept 2, 2025: City Council approved a water deal 9-2 that caps average use at 1,000 gallons a day and β¦
Stopped or cancelledabout 8 miles awayWhite Rose Partners data center (Kenyon Road and Route 25, South Elgin)
South Elgin, Kane County
20 acres
π July 2026: White Rose Partners presented plans for a 200,000-square-foot data center on farmland itβ¦
Reported in the news, not confirmed yet
Stopped or cancelledabout 10 miles awayCloud Centers data center at former Lockformer site (711 Ogden Ave., Lisle)
Lisle, DuPage County
18 acres
π March 2026: Developer told the village it withdrew its application.
Stopped or cancelledabout 11 miles awayKaris Critical data center at former Lucent campus (Naperville)
Naperville, DuPage County
π Jan 20, 2026: Naperville City Council voted 6-1 to deny the data center after months of debate and a pβ¦
Stopped or cancelledabout 12 miles awayPlum Farms rezoning for possible data center (Higgins Road and Route 59)
Hoffman Estates, Cook County
186 acres
π June 30, 2026: Landowner withdrew its rezoning request after more than 3,250 people signed a petition aβ¦
Being builtabout 13 miles awayCompass Datacenters campus at former Sears headquarters (Hoffman Estates)
Hoffman Estates, Cook County
273 acres
π Dec 2025: Village issued permits; walls for the first two data center buildings went up.
Local votes and rules
βΈοΈ Pause on new data centers
City council voted 12-0 to pause new permits and approvals for data centers and battery storage sites for 180 days while it studies new rules. A data center was already being built on Washington Street.
What you can do
- Get told first.
We'll email you if anything changes in West Chicago City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Commonwealth Edison Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Illinois.