No project in Lombard Village, but 9 nearby
Who decides here: the Village Board of Lombard Village votes on zoning. The DuPage County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Cloud Centers data center at former Lockformer site (711 Ogden Ave., Lisle)
Lisle, DuPage County
18 acres
🕒 March 2026: Developer told the village it withdrew its application.
Being builtabout 8 miles awayCyrusOne data center campus (Bryn Mawr Avenue, Wood Dale)
Wood Dale, DuPage County
62 acres
🕒 May 2025: CyrusOne finished the frame of the first 18-megawatt building.
Reported in the news, not confirmed yet
Approved, not built yetabout 10 miles awayNexstar data center campus at WGN radio transmitter site (Rohlwing Road)
Elk Grove Village, Cook County
35 acres
🕒 Jan 2026: Village Board extended the deadline to start the first building to Sept. 30, 2027; the p…
Reported in the news, not confirmed yet
Being builtabout 10 miles awayTA Realty ORD01 data center (Elmhurst and Old Higgins roads)
Elk Grove Village, Cook County
47 acres
🕒 Oct 3, 2025: Demolition was underway to make way for the 47-acre data center campus.
Reported in the news, not confirmed yet
Approved, not built yetabout 10 miles awayStream Data Centers campus (Landmeier Road area, Elk Grove Village)
Elk Grove Village, Cook County
34 acres
🕒 2025: ComEd broke ground on a 260-megawatt substation for the Stream campus.
Reported in the news, not confirmed yet
Stopped or cancelledabout 12 miles awayKaris Critical data center at former Lucent campus (Naperville)
Naperville, DuPage County
🕒 Jan 20, 2026: Naperville City Council voted 6-1 to deny the data center after months of debate and a p…
Being builtabout 12 miles awayCloudHQ data center campus at former United Airlines offices (Mount Prospect)
Mount Prospect, Cook County
50 acres
🕒 Oct 28, 2025: Village Board took up CloudHQ's request to change the plan to two three-story buildings,…
Reported in the news, not confirmed yet
Stopped or cancelledabout 15 miles awayPlum Farms rezoning for possible data center (Higgins Road and Route 59)
Hoffman Estates, Cook County
186 acres
🕒 June 30, 2026: Landowner withdrew its rezoning request after more than 3,250 people signed a petition a…
What you can do
- Get told first.
We'll email you if anything changes in Lombard Village. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Commonwealth Edison Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Illinois.