Being built

CyrusOne data center campus (Bryn Mawr Avenue, Wood Dale)

Also called: CHI6

CyrusOne is building six data center buildings on 62 acres in Wood Dale, an investment over $1 billion. The first 18-megawatt building is done or nearly done; the rest are planned through 2032.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Wood Dale City.

Where things stand: Being built First 18-megawatt building was topped out in May 2025; more buildings are planned through 2032.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (May 2025): CyrusOne finished the frame of the first 18-megawatt building.

What we know

  • 📍 WhereWest of Route 83, between Bryn Mawr Avenue and Foster Avenue (first building at 460-480 Bryn Mawr Ave.), Wood Dale, DuPage County
  • 🏢 CompanyCyrusOne
  • 🌳 Size62 acres
  • 💵 Cost$1 billion
  • 💸 Tax breaksCity expects at least $2 million a year in utility taxes.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts will the full campus use? 🙋 I'll find out ·
  • How much water will it use? 🙋 I'll find out ·
  • How many diesel backup generators are planned? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: sources put the campus west of Route 83 between Bryn Mawr Avenue and Foster Avenue. A 2024 satellite image shows a large cleared block with new roads there. The pin is in that block.

    What happened so far

    • 2024
      CyrusOne filed plans for a five-building campus, later grown to six.
    • May 2025
      CyrusOne finished the frame of the first 18-megawatt building.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. CyrusOne: Wood Dale CHI6 · Baxtel · 2026
    2. CyrusOne tops out 18MW Illinois data center · DatacenterDynamics · May 2025
    3. Bryn Mawr Avenue position, Wood Dale · OpenStreetMap Nominatim · Oct 8, 2026
    4. Sentinel-2 cloudless 2024 satellite image of the site · EOX / Copernicus Sentinel-2 · Oct 8, 2026