Being built

CloudHQ data center campus at former United Airlines offices (Mount Prospect)

CloudHQ is building a data center campus on an old airline office campus in Mount Prospect, with its own ComEd substations. In 2025 it asked to switch to two bigger three-story buildings, the first due in March 2027 and the second in December 2030.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: Broke ground in Aug. 2022. In Oct. 2025 CloudHQ asked the village to change the plan to two larger buildings; first one due March 2027.

๐Ÿ•’ Latest update (Oct 28, 2025): Village Board took up CloudHQ's request to change the plan to two three-story buildings, a second substation and a satellite antenna yard.

What we know

  • ๐Ÿ“ WhereFormer United Airlines operations center (about 50 acres), Mount Prospect, Cook County
  • ๐Ÿข CompanyCloudHQ
  • ๐ŸŒณ Size50 acres
  • โšก Power it needs300 megawatts (about as much as 240,000 homes)
  • ๐Ÿ”Œ Where the power comes fromComEd is building a dedicated substation on site.
  • ๐Ÿ—ผ New power linesYes
  • ๐Ÿ’ต Cost$2.5 billion
  • ๐Ÿ‘ท Jobs promised100

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Aug 2022
    CloudHQ and ComEd broke ground on the $2.5 billion campus.
  • Oct 28, 2025
    Village Board took up CloudHQ's request to change the plan to two three-story buildings, a second substation and a satellite antenna yard.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. New data center proposal comes before Mount Prospect board ยท Daily Herald ยท Oct 27, 2025
  2. CloudHQ breaks ground on $2.5 billion Chicago data center campus ยท Data Center Frontier ยท Aug 2022
  3. CloudHQ Mount Prospect ORD campus ยท Baxtel ยท 2026
  4. CloudHQ ORD Campus (300 MW, under construction) ยท Data Center Census ยท 2026

See something wrong? Tell us and we'll fix it.