Lowndes County
- ❓ Exactly where is the site, and is any of it inside a town?
About Project Red Clay data center in Lowndes County in Unincorporated Lowndes County - 📄 Did county officials sign an agreement to keep the plans private (NDA)?
About Project Red Clay data center in Lowndes County in Unincorporated Lowndes County - 📄 Where exactly is the site? A parcel number, address or agenda link helps.
About Project Red Clay data center in Lowndes County in Unincorporated Lowndes County - ❓ What will the court decide in the residents' lawsuit over the Oct. 13 vote?
About Project Red Clay data center in Lowndes County in Unincorporated Lowndes County - ❓ How big is the site? Earlier reports said about 800 acres; November 2026 reports say 2,200 acres.
About Project Red Clay data center in Lowndes County in Unincorporated Lowndes County - 📄 What will the court decide in the second lawsuit, over open meetings and open records?
About Project Red Clay data center in Lowndes County in Unincorporated Lowndes County
Mobile County
- ❓ Is the building permit still valid?
About Edged data center on Telegraph Road, Prichard in Prichard City - ❓ How much power and water will the data center use?
About Edged data center on Telegraph Road, Prichard in Prichard City - ❓ Will the developer sue the city?
About Edged data center on Telegraph Road, Prichard in Prichard City - ❓ Did the Prichard Planning Commission approve the site plan, and does the city now treat the building permit as valid?
About Edged data center on Telegraph Road, Prichard in Prichard City - ❓ How many megawatts will the campus use?
About Beacon Calvert Infrastructure Hub in Unincorporated Mobile County - ❓ Which company will use it?
About Beacon Calvert Infrastructure Hub in Unincorporated Mobile County - ❓ Has Alabama Power agreed to serve it?
About Beacon Calvert Infrastructure Hub in Unincorporated Mobile County - 📄 Where exactly is the site? A parcel number, address or agenda link helps.
About Beacon Calvert Infrastructure Hub in Unincorporated Mobile County
Tuscaloosa County
- ❓ Which company will use the data center?
About Applied Digital Delta Forge 2 AI data center, Brookwood in Brookwood City - ❓ How much water will it use per day?
About Applied Digital Delta Forge 2 AI data center, Brookwood in Brookwood City - ❓ How many diesel backup generators will it have?
About Applied Digital Delta Forge 2 AI data center, Brookwood in Brookwood City - 📄 Where exactly is the site? A parcel number, address or agenda link helps.
About Applied Digital Delta Forge 2 AI data center, Brookwood in Brookwood City - ❓ Has construction started on Delta Forge 2? It was set to begin Oct. 1, 2026.
About Applied Digital Delta Forge 2 AI data center, Brookwood in Brookwood City - ❓ How big would this data center be, in megawatts?
About Project Brookwood data center campus (Youngwoo & Associates) in Brookwood City - ❓ Which company would use it?
About Project Brookwood data center campus (Youngwoo & Associates) in Brookwood City - ❓ How much water would it use?
About Project Brookwood data center campus (Youngwoo & Associates) in Brookwood City - 📄 Where exactly is the site? A parcel number, address or agenda link helps.
About Project Brookwood data center campus (Youngwoo & Associates) in Brookwood City - ❓ How many megawatts will the center use?
About University of Alabama High Performance Computing and Data Center in Tuscaloosa City
Shelby County
- ❓ How much power and water would the data center use?
About Westover data center near U.S. 280 in Westover Town - ❓ Does the pause apply to this project, since the land was already rezoned?
About Westover data center near U.S. 280 in Westover Town - ❓ Which company would use the data center?
About Westover data center near U.S. 280 in Westover Town - ❓ How much water will it use?
About Digi Power X AI data center, Columbiana in Columbiana City - ❓ How many backup generators will it have?
About Digi Power X AI data center, Columbiana in Columbiana City - ❓ Did the city or county give tax breaks?
About Digi Power X AI data center, Columbiana in Columbiana City - ❓ Has NorthPoint filed any annexation or rezoning request?
About Wilsonville hyperscale data center (NorthPoint) in Wilsonville Town - ❓ Is the land option still active?
About Wilsonville hyperscale data center (NorthPoint) in Wilsonville Town - 📄 Where exactly is the site? A parcel number, address or agenda link helps.
About Wilsonville hyperscale data center (NorthPoint) in Wilsonville Town
Jefferson County
- ❓ When will the City Council vote?
About Patmos data center in former Fairfield Walmart in Fairfield City - ❓ How much water will it use?
About Patmos data center in former Fairfield Walmart in Fairfield City - ❓ How many backup generators will it have?
About Patmos data center in former Fairfield Walmart in Fairfield City - ❓ Which company will use the data center?
About Project Marvel data center campus in Bessemer in Bessemer City - ❓ How many diesel backup generators will the campus have?
About Project Marvel data center campus in Bessemer in Bessemer City - ❓ Will Bessemer residents' power bills go up because of this project?
About Project Marvel data center campus in Bessemer in Bessemer City - ❓ How much water will the campus use, given earlier estimates of up to 2 million gallons a day?
About Project Marvel data center campus in Bessemer in Bessemer City - ❓ Is RSTL LLC, which owns about 1,600 acres on Rock Mountain Lake Road and Old Lawsontown Road, the land company behind Project Marvel?
About Project Marvel data center campus in Bessemer in Bessemer City - ❓ How much water will it use per day?
About Nebius AI data center in Oxmoor Valley, Birmingham in Birmingham City - ❓ How many diesel backup generators will it have?
About Nebius AI data center in Oxmoor Valley, Birmingham in Birmingham City - ❓ How will the lawsuits by neighbors and the Humane Society end?
About Nebius AI data center in Oxmoor Valley, Birmingham in Birmingham City
Morgan County
- ❓ Has the bitcoin mine started running?
About Bitcoin mining data center on Union Road near Somerville in Unincorporated Morgan County - ❓ Which utility will supply the power?
About Bitcoin mining data center on Union Road near Somerville in Unincorporated Morgan County - ❓ Is the site inside Somerville town limits?
About Bitcoin mining data center on Union Road near Somerville in Unincorporated Morgan County - ❓ One tracker lists this project as canceled; local news in August 2026 said it was still moving ahead. Which is true now?
About Bitcoin mining data center on Union Road near Somerville in Unincorporated Morgan County - 📄 Where exactly is the site? A parcel number, address or agenda link helps.
About Bitcoin mining data center on Union Road near Somerville in Unincorporated Morgan County
Jackson County
- ❓ How much water does the site use?
About Google data center at Widows Creek, Jackson County in Unincorporated Jackson County - ❓ Is the site inside Bridgeport city limits or unincorporated Jackson County?
About Google data center at Widows Creek, Jackson County in Unincorporated Jackson County
Elmore County
- ❓ Is the mill data center idea still alive or withdrawn?
About Tallassee 1852 Mill data center idea in Tallassee City - ❓ Who are the investors?
About Tallassee 1852 Mill data center idea in Tallassee City
Talladega County
- ❓ Who is the developer and who would use the data center?
About Childersburg Industrial Park data center in Childersburg City - ❓ How much water would it use?
About Childersburg Industrial Park data center in Childersburg City - ❓ Has the land sale been finalized?
About Childersburg Industrial Park data center in Childersburg City - 📄 Where exactly is the site? A parcel number, address or agenda link helps.
About Childersburg Industrial Park data center in Childersburg City
Montgomery County
- ❓ How much water will the campus use per day?
About Meta Montgomery data center in Montgomery City - ❓ How many megawatts will the full campus use?
About Meta Montgomery data center in Montgomery City - ❓ What tax breaks did Meta receive?
About Meta Montgomery data center in Montgomery City - ❓ Where exactly in Montgomery is it being built?
About DC BLOX Montgomery edge data center in Montgomery City - ❓ Which cloud company is the customer?
About DC BLOX Montgomery edge data center in Montgomery City - ❓ Which building on Bill Joseph Parkway is the DC BLOX data center? A building permit or parcel number helps.
About DC BLOX Montgomery edge data center in Montgomery City
Lee County
- ❓ How large will the Auburn site grow, in megawatts?
About Core Scientific AI computing site at AUBix, Auburn in Auburn City - ❓ How much water does it use?
About Core Scientific AI computing site at AUBix, Auburn in Auburn City
Madison County
- ❓ How much power and water does the Huntsville campus use?
About Meta Huntsville data center in Huntsville City