πŸ“£ Report Something
Being built

Nebius AI data center in Oxmoor Valley, Birmingham

Also called: Nebius AI factory, Alabama ADC Holdings

Nebius is building a 300-megawatt AI data center on a former office site in Birmingham's Oxmoor Valley. It got 30-year tax breaks from the city's development board. Neighbors worry about noise, water and power bills, and some have sued.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Construction started in mid-2026. Lawsuits by neighbors and the Humane Society are pending.

πŸ•’ Latest update (July 2026): Two neighbors sued to stop the project; a judge let construction continue for now.

What we know

  • πŸ“ Where201 Milan Parkway, off Lakeshore Parkway (former Regions operations center), Birmingham, Jefferson County
  • 🏒 CompanyNebius
  • πŸ›οΈ Owned byNebius Group
  • πŸ‘€ Built forNebius
  • 🌳 Size75 acres
  • ⚑ Power it needs300 megawatts (about as much as 240,000 homes)
  • πŸ”Œ Where the power comes fromAlabama Power; new substation paid for by Nebius
  • πŸ—Ό New power linesYes
  • ❄️ Coolingclosed-loop cooling (company says)
  • πŸ’΅ Cost$35.9 billion
  • πŸ’Έ Tax breaksBirmingham Industrial Development Board approved 65% off non-school property taxes and 80% off construction sales taxes, for up to 30 years.
  • πŸ‘· Jobs promised78

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Sept 2025
    Nebius bought the 75-acre former Regions site.
  • March 26, 2026
    City zoning board recommended Nebius's substation request, but denied an Alabama Power switching station.
  • May 2026
    City issued about $40 million in building permits to the builder.
  • May 29, 2026
    Industrial Development Board voted 6-0 for 30-year tax breaks.
  • July 2026
    Two neighbors sued to stop the project; a judge let construction continue for now.

Local votes and rules

βš–οΈ Court case

Oxmoor Valley homeowners sued the City of Birmingham, Nebius and its builder, saying the city broke its own zoning rules when it allowed the 300-megawatt data center. In July 2026 a judge ruled the case can go forward and held hearings on stopping construction. Neighbors later added claims about land sales tied to the site.

July 10, 2026

πŸ“œ Data center rules

Council voted 6-3 for new zoning rules for all sizes of data centers. The biggest ('hyperscale', over 200,000 sq ft or over 30 megawatts) must meet 20 conditions: 500 ft from homes, 1,000 ft from major transit stations, at least 5 acres, closed-loop cooling, no fossil-fuel generators except for emergencies and testing, and noise studies before and after building. A public hearing is no longer required if all conditions are met.

June 9, 2026

🀝 Agreement with the company

The city's Industrial Development Board voted 6-0 to give the Nebius data center tax breaks for up to 30 years: 65% off non-school property taxes and 80% off construction sales taxes. The mayor said the city itself did not give the tax breaks.

May 29, 2026

⏸️ Pause on new data centers

Council paused permits, site plans and business licenses for new or bigger data centers using more than 20 megawatts, for 180 days. Two projects already in the works (DC BLOX expansion and Nebius) were exempt. The pause was meant to end once new rules were in place.

March 3, 2026