Project Brookwood data center campus (Youngwoo & Associates)
Also called: Project Brookwood LLC
A New York developer, Youngwoo & Associates, got 374 acres annexed into Brookwood and rezoned for industry. Its application says it plans a data center campus. No building plans or power needs have been made public.
Where things stand: City Council annexed and rezoned 374 acres in Sept 2026. No building plans filed yet.
π Latest update (Sept 15, 2026): City Council voted unanimously to annex and rezone the land; the application lists a data center campus as the use.
What we know
- π WhereAlong Brookwood (Industrial) Parkway, across from Brookwood Middle School, west of the Applied Digital land, Brookwood, Tuscaloosa County
- π’ CompanyYoungwoo & Associates (Project Brookwood LLC)
- π³ Size374 acres
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How big would this data center be, in megawatts? π I'll find out
- Which company would use it? π I'll find out
- How much water would it use? π I'll find out
- Where exactly is the site? A parcel number, address or agenda link helps. π I'll find out
What happened so far
- Aug 11, 2026Planning and Zoning Commission unanimously recommended annexing and rezoning 374 acres to light industrial.
- Sept 15, 2026City Council voted unanimously to annex and rezone the land; the application lists a data center campus as the use.
Local votes and rules
π€ Agreement with the company
The county development board unanimously approved about $314.5 million in tax breaks over 20 years for Applied Digital's Delta Forge 2 data center in Brookwood. The company agreed to pay $270 million over 20 years to local governments.
πΊοΈ Zoning change
Council unanimously annexed 374 acres along Brookwood Industrial Parkway and rezoned it from single-family homes to light industrial for Project Brookwood LLC. The application lists a data center campus. The Planning and Zoning Commission had recommended it in August.
Drag the slider to compare the land before and now.
Where this comes from
- Brookwood council approves rezoning, annexation for 'Project Brookwood, LLC' Β· WBRC Β· Sept 16, 2026
- Records Tie Third Data Center Developer to Hundreds of Acres in Brookwood Β· Tuscaloosa Thread Β· Aug 21, 2026
- Brookwood Planning and Zoning Commission recommends rezoning request of more than 370 acres Β· WBRC Β· Aug 12, 2026
- Census geocoder result Β· U.S. Census Bureau Β· Oct 8, 2026
See something wrong? Tell us and we'll fix it.