Being built

Meta Montgomery data center

Meta is building an AI data center campus off I-65 in Montgomery, across from the Hyundai plant. In 2025 it added two more buildings, bringing the total investment to over $1.5 billion.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Under construction; first building expected online around the end of 2026. Two more buildings added in 2025.

๐Ÿ•’ Latest update (Sept 24, 2025): Meta said it would add two buildings, raising the campus to nearly 1.3 million square feet and more than $1.5 billion.

What we know

  • ๐Ÿ“ WhereOff Interstate 65, across from the Hyundai assembly plant, Montgomery, Montgomery County
  • ๐Ÿข CompanyMeta
  • ๐Ÿ›๏ธ Owned byMeta Platforms
  • ๐Ÿ‘ค Built forMeta
  • ๐Ÿ”Œ Where the power comes fromAlabama Power; Meta says it matches use with solar, including a planned 80 MW solar farm near Snowdoun
  • ๐Ÿ’ต Cost$1.5 billion
  • ๐Ÿ‘ท Jobs promised100

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • May 2, 2024
    Meta announced an $800 million data center in Montgomery.
  • Sept 24, 2025
    Meta said it would add two buildings, raising the campus to nearly 1.3 million square feet and more than $1.5 billion.

Local votes and rules

๐Ÿ—ณ๏ธ Public vote

Stockton-area voters approved zoning for their area, 215 to 161. This starts a 180-day pause on new development while a local committee drafts rules. The vote grew out of fights over a 4,500-acre solar farm that will power Meta's Montgomery data center; the county said the vote has little effect on that solar farm.

June 30, 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Governor Ivey Announces Meta Plans to Build $800 Million, Next-Generation Data Center in Montgomery ยท Office of the Governor of Alabama ยท May 2, 2024
  2. Meta to expand Montgomery data center, upping local investments to $1.5 billion ยท Alabama Political Reporter ยท Sept 24, 2025
  3. Alabama data centers multiply as artificial intelligence fuels growth ยท WBRC ยท Feb 18, 2026