1 data center project in Social Circle City
Who decides here: the City Council of Social Circle City votes on zoning. The Newton County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Meta Stanton Springs (Newton) data center campus
Unincorporated Newton County, Newton County
for Meta
🕒 May 2026: Morgan County residents near the site said their well water turned muddy; the EPA said i…
Reported in the news, not confirmed yet
Proposedabout 2 miles awaySailfish data center (Social Circle Parkway)
Social Circle, Walton County
300 acres
🕒 Dec 10, 2024: Walton County commissioners unanimously approved Social Circle's annexation request.
Approved, not built yetabout 2 miles awayEast Hightower Trail data center (Social Circle)
Social Circle, Walton County
96 acres
🕒 Nov 18, 2025: Social Circle City Council approved a special use permit for a data center on 96 acres.
Reported in the news, not confirmed yet
Proposedabout 4 miles away1402 Roy Malcom Road data center (Social Circle)
Social Circle, Walton County
123 acres
🕒 April 6, 2026: Planning commission public hearings were scheduled.
Reported in the news, not confirmed yet
Approved, not built yetabout 4 miles awayHawkins Academy Road data center (Social Circle)
Social Circle, Walton County
151 acres
🕒 Nov 2025: City council cast a series of votes to clear the way for the data center.
Being builtabout 7 miles awayAmazon Web Services data center (Alcovy Road, Covington)
Covington, Newton County
430 acres · for Amazon Web Services
🕒 Dec 15, 2025: Covington City Council approved a $100 million agreement for Amazon to build a water tre…
Reported in the news, not confirmed yet
Proposedabout 7 miles awayGregory Road data center campus
Covington, Newton County
213 acres
🕒 March 27, 2025: A data center campus of up to 1.41 million square feet on about 213 acres (plus 27 home …
What you can do
- Get told first.
We'll email you if anything changes in Social Circle City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Social Circle City: Georgia Power Co. (company) or Snapping Shoals El Member Corp. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.
🙋 Open tasks here
- Was the land annexed into Social Circle, and was it rezoned?
- Who is the end user?
- How much power will it use?