Proposed

Gregory Road data center campus

A data center campus of up to 1.4 million square feet is proposed on about 213 acres near Gregory Road in Covington, built in three phases from 2027 to 2036. The state filing values it at $5.7 billion and lists about 1.1 million gallons of water a day.

βœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Filed for state review in March 2025; first phase planned for 2027. We found no final city vote.

πŸ•’ Latest update (March 27, 2025): A data center campus of up to 1.41 million square feet on about 213 acres (plus 27 home lots) was filed for state regional review (DRI #4428).

What we know

  • πŸ“ WhereNear Gregory Road and Flat Rock Road, Covington, Newton County
  • 🏒 CompanyUniversal Planning LLC
  • 🌳 Size213 acres
  • πŸ’§ WaterNewton County Water & Sewerage Authority Β· 1,080,000 gallons a day
  • πŸ’΅ Cost$5.7 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • March 27, 2025
    A data center campus of up to 1.41 million square feet on about 213 acres (plus 27 home lots) was filed for state regional review (DRI #4428).

Local votes and rules

⏸️ Pause on new data centers

A data center tracker lists a Newton County data center pause dated July 15, 2026. Newton County already hosts Meta and Amazon data centers. Details were not found.

July 15, 2026
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

RecentRecent
Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. DRI #4428: Gregory Road Data Center (Development of Regional Impact filing) Β· Georgia Department of Community Affairs Β· March 27, 2025
  2. DRI #4428: Gregory Road Data Center, Additional Information Form Β· Georgia Department of Community Affairs Β· March 27, 2025
  3. Plans filed for 1.4 million sq ft data center campus outside Atlanta, Georgia Β· Data Center Dynamics Β· March 2025