ProposedBig (AI-size): 300 acres

Sailfish data center (Social Circle Parkway)

Sailfish Investors plans a 1.78 million-square-foot data center on more than 300 acres near Social Circle Parkway. The state filing values it at $7.4 billion. Sailfish said it was talking with several very large cloud companies.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Social Circle City.

Where things stand: Proposed Walton County approved the city's annexation request on Dec. 10, 2024. We did not find the final city rezoning vote.

❓ 3 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (Dec 10, 2024): Walton County commissioners unanimously approved Social Circle's annexation request.

What we know

  • 📍 Where300+ acres at Amber Stapp Studdard Road near Social Circle Parkway, Social Circle, Walton County
  • 🏢 CompanySailfish Investors Acquisitions, LLC
  • 🏛️ Owned bySailfish Investors
  • 🌳 Size300 acres
  • 💧 WaterCity of Social Circle · 20,000 gallons a day
  • 💵 Cost$7.4 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Nov 15, 2024
      A 1.79 million square foot data center filed for state regional review (DRI #4329).
    • Dec 10, 2024
      Walton County commissioners unanimously approved Social Circle's annexation request.

    Local votes and rules

    ✋ Turned down

    Social Circle's planning commission voted unanimously against recommending annexation, land-use changes, rezoning and a special use for a 150-acre, 288-megawatt data center at Hawkins Academy Road and Roy Malcom Road. The applicant said the end user was secret under a non-disclosure agreement. This was a recommendation; the city council makes the final decision.

    Sept 23, 2025

    ⏸️ Pause on new data centers

    Social Circle's city council voted unanimously for a 90-day pause on new data center applications while it reviewed proposals already in hand.

    Sept 16, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. DRI #4329: Data Center - 0 Social Circle Parkway (Development of Regional Impact filing) · Georgia Department of Community Affairs · Nov 15, 2024
    2. DRI #4329: Data Center - 0 Social Circle Parkway, Additional Information Form · Georgia Department of Community Affairs · Nov 15, 2024
    3. Data center in Social Circle could see opening in 2027 · The Walton Tribune · Dec 10, 2024