3 data center projects in South Fulton City
Who decides here: the City Council of South Fulton City votes on zoning. The Fulton County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In South Fulton City
Vantage data center (Westlake site, South Fulton)
South Fulton, Fulton County
🕒 Aug 13, 2024: Vantage filed a 754,000 square foot data center for state regional review (DRI #4256).
ProposedVantage data center (Stacks Road site, South Fulton)
South Fulton, Fulton County
🕒 Aug 13, 2024: Vantage filed a 697,000 square foot data center for state regional review (DRI #4257).
ProposedStonewall Tell data center (RSC Investment Management)
South Fulton, Fulton County
59 acres
🕒 Dec 6, 2024: RSC filed a 1.9 million square foot data center for state regional review (DRI #4342).
Nearby (within 15 miles)
ATL11 data center (Stonewall Tell Road)
Union City, Fulton County
🕒 July 15, 2024: A 2.1 million square foot data center was filed for state regional review (DRI #4235).
Approved, not built yetabout 2 miles awayMicrosoft Union City data center campus (Stonewall Tell Road)
Union City, Fulton County
136 acres · for Microsoft
🕒 April 2024: Microsoft bought 136 acres in Fulton County for $53.5 million.
Reported in the news, not confirmed yet
Proposedabout 2 miles awayMicrosoft ATL50 data center
Union City, Fulton County
88.01 acres · for Microsoft
🕒 Sept 15, 2026: Union City filed Microsoft's ATL50 for state regional review (DRI #4843): two 3-story bu…
Proposedabout 4 miles awayThe Crossing Business Park data center campus (Union City)
Union City, Fulton County
232.15 acres
🕒 Oct 29, 2026: Union City filed The Crossing Business Park for state regional review (DRI #4825): a dat…
Proposedabout 6 miles awayVantage Data Centers Douglasville campus
Douglasville, Douglas County
90 acres
🕒 Aug 15, 2023: Vantage filed a three-building, 1.66 million square foot campus for state regional revie…
Proposedabout 6 miles awayTA Realty ATL03 / Red Oak data center
Union City, Fulton County
67.8 acres
🕒 Oct 31, 2024: TA Realty filed four data center buildings (about 1 million square feet) for state regio…
Proposedabout 8 miles awayAmazon Web Services land for data center (Echo Road, Douglas County)
Unincorporated Douglas County, Douglas County
118 acres · for Amazon Web Services
🕒 Oct 2024: Amazon confirmed it bought 118 acres in Douglas County and is exploring a data center th…
Reported in the news, not confirmed yet
Proposedabout 8 miles awayT5 ATL IV data center campus (Gullatt Road, Fairburn)
Fairburn, Fulton County
91 acres
🕒 May 5, 2025: T5 filed T5 ATL IV for state regional review (DRI #4465): up to 2.2 million square feet.
Approved, not built yetabout 8 miles awayMicrosoft data center (Project Rita, Tyrone)
Tyrone, Fayette County
161 acres · for Microsoft
🕒 Aug 6, 2026: Town staff presented a review of data center rules to the council.
What you can do
- Get told first.
We'll email you if anything changes in South Fulton City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in South Fulton City: Georgia Power Co. (company) or Greystone Power Corporation (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Georgia.
🙋 Open tasks here
- Who is the end user?
- How much power will it use?
- Has South Fulton approved it?
- How much power will it use?
- Has construction started?
- How much power will it use?