Vantage Data Centers filed plans for three data center buildings, about 1.7 million square feet, in Douglasville in 2023. It was the company's first Georgia project.
Where things stand: Filed for state review in Aug. 2023 with a December 2025 target. We did not confirm construction.
๐ Latest update (Aug 15, 2023): Vantage filed a three-building, 1.66 million square foot campus for state regional review (DRI #4051).
What we know
- ๐ WhereNear Roberts Road, Douglasville, Douglas County
- ๐ข CompanyVantage Data Center Management Company
- ๐๏ธ Owned byVantage Data Centers
- ๐ง WaterDouglas County Water Sewer Authority ยท 14,000 gallons a day
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is it under construction or running now? ๐ I'll find out
- How much power will it use? ๐ I'll find out
What happened so far
- Aug 15, 2023Vantage filed a three-building, 1.66 million square foot campus for state regional review (DRI #4051).
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- DRI #4051: Vantage Data Center (Development of Regional Impact filing) ยท Georgia Department of Community Affairs ยท Aug 15, 2023
- Vantage plots data center campus in Atlanta, Georgia ยท Data Center Dynamics ยท 2023