Vantage Data Centers Douglasville campus
Vantage Data Centers filed plans for three data center buildings, about 1.7 million square feet, in Douglasville in 2023. It was the company's first Georgia project.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Douglasville City.
Where things stand: Proposed Filed for state review in Aug. 2023 with a December 2025 target. We did not confirm construction.
❓ 2 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (Aug 15, 2023): Vantage filed a three-building, 1.66 million square foot campus for state regional review (DRI #4051).
What we know
- 📍 WhereRoberts Road, Douglasville, Douglas County
- 🏢 CompanyVantage Data Center Management Company
- 🏛️ Owned byVantage Data Centers
- 🌳 Size90 acres
- 💧 WaterDouglas County Water Sewer Authority · 14,000 gallons a day
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is it under construction or running now? 🙋 I'll find out ·
- How much power will it use? 🙋 I'll find out ·
What happened so far
- Aug 15, 2023Vantage filed a three-building, 1.66 million square foot campus for state regional review (DRI #4051).
Drag the slider to compare the land before and now.
Where this comes from
- DRI #4051: Vantage Data Center (Development of Regional Impact filing) · Georgia Department of Community Affairs · Aug 15, 2023
- Vantage plots data center campus in Atlanta, Georgia · Data Center Dynamics · 2023
- DRI #4051 Initial Information Form: Vantage Data Center (location field) · Georgia Department of Community Affairs · Oct 7, 2026
- Douglas County tax parcel 0169-015-0004 (county parcel map service) · Douglas County · Oct 7, 2026
- Vantage Entering New Market With 1.7M SF Atlanta Data Center Campus · Bisnow · Aug 21, 2023
See something wrong? Tell us and we'll fix it.