Centra Logistics data centers off Darbytown Road (Varina)
Henrico County, Henrico County
200 acres
🕒 Feb 26, 2026: Board of Zoning Appeals denied Centra's vested-rights appeal.
Reported in the news, not confirmed yet
ProposedIron Mountain data center campus (White Oak Technology Park)
Henrico County, Henrico County
66 acres
🕒 Feb 2025: Iron Mountain announced the Henrico campus.
Reported in the news, not confirmed yet
ProposedDC Blox data center at the former Azalea Flea Market site
Henrico County, Henrico County
5 acres
🕒 Jan 16, 2025: DC Blox bought the property.
Reported in the news, not confirmed yet
Approved, not built yetQTS RIC4 and RIC5 expansions (White Oak / Varina)
Henrico County, Henrico County
1,100 acres
🕒 2026: QTS applied to the Virginia DEQ to permit 370 more diesel generators.
Reported in the news, not confirmed yet
Nearby (within 15 miles)
Digital Drive campus (Chirisa and PowerHouse, Meadowville)
Chesterfield County, Chesterfield County
104 acres
🕒 Sept 26, 2024: PowerHouse and Chirisa announced the land purchase.
Reported in the news, not confirmed yet
Being builtabout 6 miles awayGoogle Project Peanut (2700 Bermuda Hundred Road)
Chesterfield County, Chesterfield County
307 acres · for Google
🕒 Oct 30, 2026: State environmental regulators (DEQ) sent a second notice of violation, this time about …
Reported in the news, not confirmed yet
Proposedabout 10 miles awayData center at former Hopewell ethanol plant
Hopewell, Hopewell city
🕒 Feb 2026: NS Development Partners bought the former ethanol plant site.
Reported in the news, not confirmed yet
Stopped or cancelledabout 15 miles awayRoxbury Technology Park (Diode Ventures)
Charles City County, Charles City County
515 acres
🕒 Aug 18, 2025: Diode Ventures withdrew the project.
Local votes and rules
📜 Data center rules
Supervisors unanimously ended by-right data centers anywhere in the county, including White Oak Technology Park. New data centers need a provisional use permit and a public hearing, and must be at least 500 feet from homes.
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated Henrico County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Virginia Electric & Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Virginia.
🙋 Open tasks here
- Has DEQ approved the new generator permit?
- How much water will the new buildings use?
- Will Centra go to court?
- Has the county approved the site plan?
- How many megawatts and buildings, and when will it open?