Centra Logistics planned eight data center buildings off Darbytown Road. Henrico changed its rules so every data center needs a permit and a public hearing. Centra said it should be allowed under the old rules, but the Board of Zoning Appeals voted unanimously against it.
Where things stand: County said the permit would be denied; the zoning appeals board rejected Centra's vested-rights appeal in February 2026.
๐ Latest update (Feb 26, 2026): Board of Zoning Appeals denied Centra's vested-rights appeal.
What we know
- ๐ WhereOff Darbytown Road, Varina, Henrico County, Henrico County
- ๐ข CompanyCentra Logistics
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Will Centra go to court? ๐ I'll find out
What happened so far
- Feb 26, 2026Board of Zoning Appeals denied Centra's vested-rights appeal.
Local votes and rules
๐ Data center rules
Supervisors unanimously ended by-right data centers anywhere in the county, including White Oak Technology Park. New data centers need a provisional use permit and a public hearing, and must be at least 500 feet from homes.