Google Project Peanut (2700 Bermuda Hundred Road)
Google is building its first Chesterfield data center at 2700 Bermuda Hundred Road, next to Meadowville Technology Park. It expects it to open in late 2027 and be fully built in 2028. The county froze Google's data center equipment tax rate here for 30 years.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Chesterfield County Board of Supervisors (for land outside city and town limits).
Where things stand: Being built Under construction; first building due late 2027. State regulators sent a second violation notice about stormwater on Oct. 30, 2026.
❓ 2 open questions about it: see below.
Last checked Nov 16, 2026.
🕒 Latest update (Oct 30, 2026): State environmental regulators (DEQ) sent a second notice of violation, this time about stormwater controls on the site (for example missing silt fences and work started before downhill controls were done). DEQ asked for a formal reply; next steps could include a consent agreement requiring fixes.
What we know
- 📍 Where2700 Bermuda Hundred Road, next to Meadowville Technology Park, Chesterfield County, Chesterfield County
- 🏢 CompanyGoogle
- 👤 Built forGoogle
- 🌳 Size307 acres
- 💸 Tax breaksCounty froze its 24-cent data center equipment tax rate for 30 years at this site.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water will this site use, and is it part of the 8.6 million gallons a day the county lists for all Google sites? 🙋 I'll find out ·
- Will DEQ fine Google for the runoff at the Project Peanut site? 🙋 I'll find out ·
What happened so far
- 2026Construction started.
- Sept 29, 2026State environmental regulators (DEQ) sent Google's site company a notice of violation for seven mud (sediment) runoff events from December 2025 to August 2026 that hurt streams and wetlands. Google says heavy rain caused it and it paused most construction to clean up.
- Oct 30, 2026State environmental regulators (DEQ) sent a second notice of violation, this time about stormwater controls on the site (for example missing silt fences and work started before downhill controls were done). DEQ asked for a formal reply; next steps could include a consent agreement requiring fixes.
Local votes and rules
✋ Turned down
The county zoning appeals board unanimously ruled that an 89-acre site at 1931 Old Bermuda Hundred Road in Chester has no 'vested right' to a data center without a conditional use permit. The owner can still apply for the permit.
🗺️ Zoning change
In its rewritten zoning code (called ZOMod), the county ended by-right data centers. They are allowed only in the new Employment Center and Employment General districts, with a conditional use permit and public hearings. The new code took effect January 1, 2026.
Drag the slider to compare the land before and now.
Where this comes from
- Chesterfield says it won't approve any more data center projects · Richmond BizSense · Aug 27, 2026
- Google files plans for first data center facilities in eastern Chesterfield · Richmond BizSense · Nov 11, 2025
- Nominatim geocode: 2700 Bermuda Hundred Road · OpenStreetMap Nominatim · Oct 8, 2026
- State regulators allege environmental violations at Google data center site in Chesterfield · WWBT 12 On Your Side · Oct 5, 2026
- Google's Project Peanut gets second DEQ violation notice · VPM News · Nov 10, 2026
See something wrong? Tell us and we'll fix it.