Approved, not built yetBig (AI-size): 1,100 acres

QTS RIC4 and RIC5 expansions (White Oak / Varina)

QTS is adding up to 17 data centers on 1,100 acres in Varina near White Oak Technology Park: up to 10 at RIC4 (478 acres) and up to 7 at RIC5 (622 acres). Its overall campus would reach 26 buildings. QTS asked the state for 370 more diesel backup generators on top of 544 already allowed.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Henrico County Board of Supervisors (for land outside city and town limits).

Where things stand: Approved, not built yet Plans approved by the county; QTS applied to state regulators for 370 more diesel backup generators in 2026.

❓ 2 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (2026): QTS applied to the Virginia DEQ to permit 370 more diesel generators.

What we know

  • 📍 WhereTechnology Boulevard and East Williamsburg Road (3250 and 3555 E. Williamsburg Rd.), Varina, Henrico County, Henrico County
  • 🏢 CompanyQTS Data Centers
  • 🏛️ Owned byBlackstone
  • 🌳 Size1,100 acres
  • 🛢️ Diesel generators370

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has DEQ approved the new generator permit? 🙋 I'll find out ·
  • How much water will the new buildings use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • 2024
      The RIC5 site was rezoned.
    • April 2024
      QTS bought the RIC4 land from the Henrico Economic Development Authority for $43.8 million.
    • 2026
      QTS applied to the Virginia DEQ to permit 370 more diesel generators.

    Local votes and rules

    📜 Data center rules

    Supervisors unanimously ended by-right data centers anywhere in the county, including White Oak Technology Park. New data centers need a provisional use permit and a public hearing, and must be at least 500 feet from homes.

    June 10, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Data center giant QTS progressing on 1,100-acre expansion that would add 17 buildings to its Henrico hub · Richmond BizSense · May 18, 2026
    2. White Oak Technology Park 2 QTS — site location · OpenStreetMap contributors (ODbL) · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.