No project in Keller City, but 8 nearby
Who decides here: the City Council of Keller City votes on zoning. The Tarrant County may review big projects too.
Nearby (within 15 miles)
Circle T data center (Westlake, near Keller)
Westlake, Tarrant County
90 acres
π Aug 18, 2026: Keller City Council voted to take legal action against Westlake over the project.
Being builtabout 4 miles awayQTS Fort Worth campus expansion (FTW1, 14100 Park Vista Blvd.)
Fort Worth, Tarrant County
53 acres
π 2026: QTS filed a $300 million, 147,946 sq ft addition (FTW1 DC1 Expansion), July 2026 to Oct.β¦
Reported in the news, not confirmed yet
Proposedabout 6 miles awayColovore Alliance AI data center (AllianceTexas)
Fort Worth, Denton County
π Sept 30, 2026: Colovore filed plans for a $430 million, 156,500 sq ft liquid-cooled data center.
Reported in the news, not confirmed yet
Proposedabout 6 miles awayProvident data center (old Santander site, Rufe Snow Drive)
North Richland Hills, Tarrant County
π June 23, 2026: Hundreds of residents attended Provident's information meeting and questioned the develoβ¦
Reported in the news, not confirmed yet
Proposedabout 12 miles awayEdged data center (Veale Ranch, west Fort Worth)
Fort Worth, Tarrant County
186 acres
π March 31, 2026: City Council voted to delay a decision on a 50% tax break.
Approved, not built yetabout 12 miles awayBlack Mountain data center campus (southeast Fort Worth)
Fort Worth, Tarrant County
431 acres
π Aug 2026: City Council approved a revised plan with a substation and setbacks of more than 300 feeβ¦
What you can do
- Get told first.
We'll email you if anything changes in Keller City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Keller City: Oncor Electric Delivery Company LLC (company) or United Electric Co-op Service Inc. (co-op (owned by its members)) or Tri-county Electric Co-op, Inc. (co-op (owned by its members)) or Denton County Electric Co-op, Inc. (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.