Status unclearBig (AI-size): 300 megawatts

Circle T data center (Westlake, near Keller)

Developers want to build four data center buildings using 300 megawatts on 90 acres of Circle T Ranch in Westlake, right next to Keller homes. Neighbors sued, saying Westlake did not give proper public notice, and a judge paused the town's vote.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Town Council of Westlake Town.

Where things stand: Status unclear Planning board approved the site plan Aug. 4, 2026. A judge lifted the order blocking the Town Council vote on Sept. 25, but the neighbors' lawsuit continues; the result of the Oct. 23 hearing has not been reported.

❓ 3 open questions about it: see below.

Last checked Nov 2, 2026.

🕒 Latest update (Sept 25, 2026): A Tarrant County district judge ended the temporary order that had blocked the Westlake Town Council from approving the development agreement. The lawsuit by a Keller homeowners association, joined by the City of Keller, continues. Mediation did not reach a settlement.

What we know

  • 📍 WhereCircle T Ranch, on the Westlake-Keller border, about 500 feet from some Keller backyards, Westlake, Tarrant County
  • 🏢 CompanyAmerican Real Estate Partners and PowerHouse Data Centers
  • 🌳 Size90 acres
  • ⚡ Power it needs300 megawatts (about as much as 240,000 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the Town Council approve the development agreement? 🙋 I'll find out ·
  • How much water will it use? 🙋 I'll find out ·
  • What did the judge decide at the Oct. 23, 2026 hearing on whether the neighbors can keep their lawsuit going? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 7, 2026: We checked the site location: approximate location found.
    • Oct 26, 2026: We checked the news for the result of the Oct. 23 court hearing and found no report yet.
    • Nov 2, 2026: We checked news searches for the result of the Oct. 23, 2026 court hearing on whether the neighbors can keep their lawsuit going and found no report.

    What happened so far

    • Aug 4, 2026
      Westlake Planning and Zoning Commission approved the site plan.
    • Aug 17, 2026
      A Tarrant County judge issued a temporary order blocking the Town Council from approving the deal; council delayed its vote.
    • Aug 18, 2026
      Keller City Council voted to take legal action against Westlake over the project.
    • Sept 25, 2026
      A Tarrant County district judge ended the temporary order that had blocked the Westlake Town Council from approving the development agreement. The lawsuit by a Keller homeowners association, joined by the City of Keller, continues. Mediation did not reach a settlement.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Westlake Planning & Zoning Commission approves data center site plan near Keller · Community Impact · Aug 5, 2026
    2. Westlake data center agreement temporarily blocked by Tarrant County court · KERA News · Aug 18, 2026
    3. Judge signs TRO blocking Westlake data center vote · Dallas Express · Aug 2026
    4. OpenStreetMap search: 13572 North Main Street, Westlake · OpenStreetMap contributors · Oct 7, 2026
    5. TDLR TABS TABS2027002672: DAL130 - Data Center (Circle T Owner LP), 13572 N. Main Street, Westlake · Texas Department of Licensing and Regulation · Oct 7, 2026
    6. Judge dissolves restraining order tied to Westlake data center. Keller's lawsuit is ongoing · The Dallas Morning News (via Yahoo News) · Sept 28, 2026
    7. Westlake data center temporary restraining order expires · FOX 4 News · Sept 25, 2026

    See something wrong? Tell us and we'll fix it.