Prime Data Centers DFW04 campus (Aledo Road and Chapin School Road)

Prime plans three data center buildings in west Fort Worth, each about 48 megawatts. The first building costs about $545 million.

πŸ‘₯ Reported, not confirmed yetSourceLast checked: Oct 6, 2026

Where things stand: First of three buildings set to be built Sept. 2024 to Jan. 2026.

πŸ•’ Latest update (Sept 2024): Construction of the first 48 MW, $545 million building was set to begin.

What we know

  • πŸ“ WhereAledo Road and Chapin School Road, west Fort Worth, Fort Worth, Tarrant County
  • 🏒 CompanyPrime Data Centers
  • πŸ’΅ Cost$545 million

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Sept 2024
    Construction of the first 48 MW, $545 million building was set to begin.

Local votes and rules

βœ… Approved

Fort Worth City Council approved zoning changes and a revised site plan for 187 acres of Black Mountain's planned $10 billion data center campus in southeast Fort Worth, near Lon Stephenson Road and Forest Hill Drive. The revised plan has taller buildings (up to 70 feet) but about half the floor space, with more than 300 feet between buildings and nearby homes. The vote was reported as 7-4.

Aug 25, 2026

⏸️ Pause on new data centers

Fort Worth City Council voted unanimously to start the process for a 90-day pause on new data centers. The first public hearing is set for November 10, 2026, and the city lists February 16, 2027 as the likely date for the final vote. Existing sites and projects already in the pipeline would not be covered.

Aug 11, 2026

πŸ“œ Data center rules

Fort Worth City Council adopted new application requirements for data centers, including showing state power grid approval before applying for city permits, and new water and wastewater design rules. It also created a Data Center and Infrastructure Commission, with 11 voting members, to study power, water, land use and money effects. Its report is due November 3, 2026.

Aug 11, 2026

βœ‹ Turned down

Fort Worth's Zoning Commission voted 7-4 to recommend against proposed data center zoning rules, saying it had too little time to review them. The rules would have kept data centers 250 feet from homes and only in industrial areas.

July 8, 2026
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

RecentRecent
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Prime files for two data center campuses in Dallas Fort Worth Β· DatacenterDynamics Β· 2024

See something wrong? Tell us and we'll fix it.