Edged data center (Veale Ranch, west Fort Worth)

Also called: Edged Energy Outpost

Edged wants to build a $1.1 billion data center on 186 acres of industrial land in west Fort Worth. The company says it will use almost no water. The City Council put off a tax break vote after residents raised concerns.

βœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Land rezoned June 2025; City Council delayed a 50% tax break vote on Mar. 31, 2026.

πŸ•’ Latest update (March 31, 2026): City Council voted to delay a decision on a 50% tax break.

What we know

  • πŸ“ Where9999 Chapin School Road, near I-20, south edge of Benbrook, Fort Worth, Tarrant County
  • 🏒 CompanyEdged Data Centers
  • πŸ›οΈ Owned byEndeavour
  • 🌳 Size186 acres
  • ❄️ CoolingCompany says it will be 'waterless'.
  • πŸ’΅ Cost$1.1 billion
  • πŸ’Έ Tax breaksCompany asked for a 50% city tax break; council delayed the vote on Mar. 31, 2026.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • June 2025
    City Council approved rezoning of the land.
  • 2026
    State filing showed a $300 million, 488,770 sq ft first building, July 2026 to Dec. 2027.
  • March 31, 2026
    City Council voted to delay a decision on a 50% tax break.

Local votes and rules

βœ… Approved

Fort Worth City Council approved zoning changes and a revised site plan for 187 acres of Black Mountain's planned $10 billion data center campus in southeast Fort Worth, near Lon Stephenson Road and Forest Hill Drive. The revised plan has taller buildings (up to 70 feet) but about half the floor space, with more than 300 feet between buildings and nearby homes. The vote was reported as 7-4.

Aug 25, 2026

⏸️ Pause on new data centers

Fort Worth City Council voted unanimously to start the process for a 90-day pause on new data centers. The first public hearing is set for November 10, 2026, and the city lists February 16, 2027 as the likely date for the final vote. Existing sites and projects already in the pipeline would not be covered.

Aug 11, 2026

πŸ“œ Data center rules

Fort Worth City Council adopted new application requirements for data centers, including showing state power grid approval before applying for city permits, and new water and wastewater design rules. It also created a Data Center and Infrastructure Commission, with 11 voting members, to study power, water, land use and money effects. Its report is due November 3, 2026.

Aug 11, 2026

βœ‹ Turned down

Fort Worth's Zoning Commission voted 7-4 to recommend against proposed data center zoning rules, saying it had too little time to review them. The rules would have kept data centers 250 feet from homes and only in industrial areas.

July 8, 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Residents question data center proposal near Fort Worth, Texas Β· GovTech (Fort Worth Star-Telegram) Β· March 17, 2026
  2. 'Enough concern today': $1B data center stalls; city, residents raise questions about tax break Β· KERA News Β· April 1, 2026
  3. Edged files to develop data center in Fort Worth, Texas Β· DatacenterDynamics Β· 2026