USA › Texas › Hood County › Unincorporated Hood County

5 data center projects in Unincorporated Hood County

Who decides here: the Hood County Commissioners Court decides on zoning for land outside city and town limits. Texas counties have very few zoning powers, so land outside cities often has few local rules.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

In Unincorporated Hood County

Nearby (within 15 miles)

Local votes and rules

✋ Turned down

Hood County commissioners voted 3-1 to reject a settlement with Sailfish that would have shrunk the Comanche Circle data center from about 2,523 to about 1,375 acres in the county. They then voted unanimously to deny Sailfish's appeal of the county's decision on its on-site permit applications. The developer had warned it could sue.

Oct 13, 2026Source

⚖️ Court case

Two developers, National CRE Holdings LLC and Greenland Capital LLC, sued Hood County, saying their data center campuses (Project Red and Project Yellow) should be approved automatically because the county missed a 30-day deadline. A district judge threw out the case for good, ruling the projects were not 'development plans' under state law. The companies said they would appeal.

July 2026Source

✅ Approved

Hood County commissioners voted 3-1 to approve, without conditions, the concept plan for the Comanche Circle data center, a 2,100-acre campus planned by Sailfish near Tolar. The county had given it conditional approval in January 2026. The developer had threatened to sue. Next comes a site plan review covering drainage, water, wastewater and environmental studies.

June 9, 2026Source

✋ Turned down

Hood County commissioners voted 3-2 to reject the concept plan for Fort Spunky, a data center and power plant project by Pacifico Energy. The plan lacked key details, such as where its water would come from. Earlier, the Acton Municipal Utility District board voted to deny water service to the project.

March 2026Source

📜 Data center rules

Hood County commissioners passed stricter development permit rules for large industrial projects such as AI data centers, crypto mines and power plants. Texas counties cannot zone land, so these rules work through the county's development permit process.

March 2026Source

✋ Turned down

Hood County commissioners voted 3-2 against a six-month pause on new large industrial projects, including data centers. During the meeting, a state senator's letter to the Attorney General argued that Texas counties do not have the power to pass such pauses. At least four data centers were proposed in the county. A second try at a pause also failed.

Feb 10, 2026Source

✅ Approved

Hood County commissioners gave conditional approval to the concept plan for the Comanche Circle data center, a 2,100-acre campus that could use up to 3 gigawatts of power.

Jan 2026Source

📌 Other

Hood County commissioners voted 3-1 for a letter of support for 'Project Patriot', which was later revealed to be a data center. The site was later annexed into the City of Granbury.

July 2025Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Unincorporated Hood County.
  2. Go to county meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Unincorporated Hood County. Nothing else.

⚡ Your electric company

Depending on where you live in Unincorporated Hood County: Oncor Electric Delivery Company LLC (company) or United Electric Co-op Service Inc. (co-op (owned by its members)) or Tri-county Electric Co-op, Inc. (co-op (owned by its members)) or Texas-new Mexico Power Co. (company).

In much of Texas you can pick who sells you power, but this company owns the power lines.

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.

🙋 Open tasks here

  • How much water will it really use? The water district was told 150,000 gallons a day, but the developer later said under 50,000 for three sites.
  • Who will run the data center?
  • What air permit will the on-site gas plant need?
  • Will Sailfish sue Hood County, and what happens to the project's on-site permits now?
  • What are Sailfish's related 'Project Lion' and 'Project Panther', and where are they?
  • What happened in Pacifico's lawsuit against Hood County?
  • Has the developer found another water source?
  • Is the Fort Spunky site about 560 acres or 862 acres? News reports give different numbers.
  • Will the appeal succeed?
  • Which power plants are the sites next to, and how much power would they use?
  • Who will run the data centers?
  • Is Project Spectrum still moving forward, or was it withdrawn?
  • How much water will it use?
  • Will it get power directly from the Comanche Peak nuclear plant?
  • Are there plans to turn it into an AI data center?

How to help →