Sailfish 'Comanche Circle' data center campus (near Tolar)
Also called: Comanche Circle
Florida-based Sailfish Investors plans a 2,100-acre data center campus called Comanche Circle in Hood County near Tolar. Together with two smaller Sailfish projects, it could use up to 3 gigawatts, partly from a new on-site gas plant. Many residents oppose it over water, traffic and noise. The county says state law gives it little power to say no.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Hood County Commissioners Court (for land outside city and town limits).
Where things stand: Approved, not built yet Concept plan approved June 9, 2026. On Oct. 13, 2026 commissioners rejected a settlement that would have made the project smaller, and denied the developer's appeal on its on-site permits.
- Oct 13, 2026: Unincorporated Hood County, Hood County: project denied Source
❓ 5 open questions about it: see below.
Last checked Oct 19, 2026.
🕒 Latest update (Oct 13, 2026): Hood County Commissioners Court voted 3-1 to reject a settlement with Sailfish. The deal would have cut the project's Hood County land from about 2,523 acres to about 1,375 acres, with promises on setbacks, cooling, lights and road repairs. Commissioners then voted unanimously to deny Sailfish's appeal of the county's decision on its on-site permit applications. The developer had warned it could sue.
What we know
- 📍 WhereRural Hood County near Tolar, by the Paluxy River valley, Unincorporated Hood County, Hood County
- 🏢 CompanySailfish Investors (Sailfish Digital Ventures)
- 🌳 Size2,100 acres
- ⚡ Power it needs3,000 megawatts (about as much as 2,400,000 homes)
- 🔌 Where the power comes fromPartly a new on-site gas power plant, partly the state grid (concept plan).
- 💧 WaterGroundwater (local water district request) · 150,000 gallons a day
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water will it really use? The water district was told 150,000 gallons a day, but the developer later said under 50,000 for three sites. 🙋 I'll find out ·
- Who will run the data center? 🙋 I'll find out ·
- What air permit will the on-site gas plant need? 🙋 I'll find out ·
- Will Sailfish sue Hood County, and what happens to the project's on-site permits now? 🙋 I'll find out ·
- What are Sailfish's related 'Project Lion' and 'Project Panther', and where are they? 🙋 I'll find out ·
What happened so far
- Jan 13, 2026Hood County Commissioners Court gave the Comanche Circle concept plan conditional approval.
- June 9, 2026Commissioners Court approved the concept plan without conditions, 3-1.
- Sept 8, 2026Hood County commissioners moved an item on several proposed data center projects, including Comanche Circle, to Oct. 13 so a public hearing could be properly advertised.
- Oct 13, 2026Hood County Commissioners Court voted 3-1 to reject a settlement with Sailfish. The deal would have cut the project's Hood County land from about 2,523 acres to about 1,375 acres, with promises on setbacks, cooling, lights and road repairs. Commissioners then voted unanimously to deny Sailfish's appeal of the county's decision on its on-site permit applications. The developer had warned it could sue.
Local votes and rules
✋ Turned down
Hood County commissioners voted 3-1 to reject a settlement with Sailfish that would have shrunk the Comanche Circle data center from about 2,523 to about 1,375 acres in the county. They then voted unanimously to deny Sailfish's appeal of the county's decision on its on-site permit applications. The developer had warned it could sue.
⚖️ Court case
Two developers, National CRE Holdings LLC and Greenland Capital LLC, sued Hood County, saying their data center campuses (Project Red and Project Yellow) should be approved automatically because the county missed a 30-day deadline. A district judge threw out the case for good, ruling the projects were not 'development plans' under state law. The companies said they would appeal.
✅ Approved
Hood County commissioners voted 3-1 to approve, without conditions, the concept plan for the Comanche Circle data center, a 2,100-acre campus planned by Sailfish near Tolar. The county had given it conditional approval in January 2026. The developer had threatened to sue. Next comes a site plan review covering drainage, water, wastewater and environmental studies.
✋ Turned down
Hood County commissioners voted 3-2 to reject the concept plan for Fort Spunky, a data center and power plant project by Pacifico Energy. The plan lacked key details, such as where its water would come from. Earlier, the Acton Municipal Utility District board voted to deny water service to the project.
📜 Data center rules
Hood County commissioners passed stricter development permit rules for large industrial projects such as AI data centers, crypto mines and power plants. Texas counties cannot zone land, so these rules work through the county's development permit process.
✋ Turned down
Hood County commissioners voted 3-2 against a six-month pause on new large industrial projects, including data centers. During the meeting, a state senator's letter to the Attorney General argued that Texas counties do not have the power to pass such pauses. At least four data centers were proposed in the county. A second try at a pause also failed.
✅ Approved
Hood County commissioners gave conditional approval to the concept plan for the Comanche Circle data center, a 2,100-acre campus that could use up to 3 gigawatts of power.
📌 Other
Hood County commissioners voted 3-1 for a letter of support for 'Project Patriot', which was later revealed to be a data center. The site was later annexed into the City of Granbury.
Drag the slider to compare the land before and now.
Where this comes from
- Hood County approves Comanche Circle data center without conditions after contentious meeting · KERA News (via KWBU) · June 10, 2026
- Eight data centers threaten to transform this small Texas county. Local officials say they have no power to stop them. · The Texas Tribune · June 2, 2026
- Texas data centers map and list · Cleanview (tracker) · Oct 2026
- Hood County data center projects head to commissioners vote · NBC DFW · Sept 8, 2026
- Hood County rejects Comanche Circle data center settlement, permit appeal · Texas Public Radio (KERA) · Oct 13, 2026
- Hood County rejects Comanche Circle data center settlement, permit appeal · KERA · Oct 13, 2026
See something wrong? Tell us and we'll fix it.