Built & runningBig (AI-size): 300 megawatts

MARA (Marathon) bitcoin mining data center (Granbury area)

Also called: Marathon Digital Granbury

Marathon Digital (MARA) runs a large bitcoin mining data center in Hood County near Granbury. It bought the site in January 2024 from Generate Capital. MARA's annual report lists 300 megawatts of total capacity there (232 megawatts running at the end of 2024). Residents nearby have complained for years about noise from crypto mining in the county.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

Where things stand: Built & running Running; Marathon bought the site in 2023.

❓ 1 open question about it: see below.

📣 Report noise, water or power bill changes

Last checked Oct 10, 2026.

🕒 Latest update (Jan 12, 2024): MARA bought the Granbury bitcoin mining site (and one in Nebraska) from Generate Capital's GC Data Center.

What we know

  • 📍 WhereNext to the Wolf Hollow power plant area, Hood County, Unincorporated Hood County, Hood County
  • 🏢 CompanyMarathon Digital Holdings (MARA)
  • 👤 Built forMarathon (bitcoin mining)
  • ⚡ Power it needs300 megawatts (about as much as 240,000 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Are there plans to turn it into an AI data center? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: exact site found in state records or maps. A satellite image shows the site.

    What happened so far

    • 2023
      Marathon Digital bought the Granbury site from Generate Capital for $178.6 million.
    • Jan 12, 2024
      MARA bought the Granbury bitcoin mining site (and one in Nebraska) from Generate Capital's GC Data Center.

    Local votes and rules

    ✋ Turned down

    Hood County commissioners voted 3-1 to reject a settlement with Sailfish that would have shrunk the Comanche Circle data center from about 2,523 to about 1,375 acres in the county. They then voted unanimously to deny Sailfish's appeal of the county's decision on its on-site permit applications. The developer had warned it could sue.

    Oct 13, 2026

    ⚖️ Court case

    Two developers, National CRE Holdings LLC and Greenland Capital LLC, sued Hood County, saying their data center campuses (Project Red and Project Yellow) should be approved automatically because the county missed a 30-day deadline. A district judge threw out the case for good, ruling the projects were not 'development plans' under state law. The companies said they would appeal.

    July 2026

    ✅ Approved

    Hood County commissioners voted 3-1 to approve, without conditions, the concept plan for the Comanche Circle data center, a 2,100-acre campus planned by Sailfish near Tolar. The county had given it conditional approval in January 2026. The developer had threatened to sue. Next comes a site plan review covering drainage, water, wastewater and environmental studies.

    June 9, 2026

    ✋ Turned down

    Hood County commissioners voted 3-2 to reject the concept plan for Fort Spunky, a data center and power plant project by Pacifico Energy. The plan lacked key details, such as where its water would come from. Earlier, the Acton Municipal Utility District board voted to deny water service to the project.

    March 2026

    📜 Data center rules

    Hood County commissioners passed stricter development permit rules for large industrial projects such as AI data centers, crypto mines and power plants. Texas counties cannot zone land, so these rules work through the county's development permit process.

    March 2026

    ✋ Turned down

    Hood County commissioners voted 3-2 against a six-month pause on new large industrial projects, including data centers. During the meeting, a state senator's letter to the Attorney General argued that Texas counties do not have the power to pass such pauses. At least four data centers were proposed in the county. A second try at a pause also failed.

    Feb 10, 2026

    ✅ Approved

    Hood County commissioners gave conditional approval to the concept plan for the Comanche Circle data center, a 2,100-acre campus that could use up to 3 gigawatts of power.

    Jan 2026

    📌 Other

    Hood County commissioners voted 3-1 for a letter of support for 'Project Patriot', which was later revealed to be a data center. The site was later annexed into the City of Granbury.

    July 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Marathon Digital: Granbury, TX Data Center · Baxtel (tracker) · 2026
    2. Eight data centers threaten to transform this small Texas county. Local officials say they have no power to stop them. · The Texas Tribune · June 2, 2026
    3. OpenStreetMap: MARA Data Center (operator Marathon Digital Holdings) · OpenStreetMap · Oct 8, 2026
    4. MARA Holdings Form 10-K for 2024 · U.S. SEC (company filing) · Feb 2025

    See something wrong? Tell us and we'll fix it.