'Fort Spunky' data center (Pacifico Energy, Hood County)
Also called: Fort Spunky
Pacifico Energy proposed an 862-acre data center called Fort Spunky that would take 100 megawatts from the grid and up to 20,000 gallons of water a day. Hood County first approved its concept plan, but revoked it 3-2 after a local water utility board denied the water request. Pacifico then sued the county.
What happens next?
Where things stand: Stopped or cancelled County revoked its earlier approval 3-2 after a water utility refused service; the developer sued the county.
❓ 3 open questions about it: see below.
📣 See work going on anyway? Tell us
Last checked Oct 10, 2026.
🕒 Latest update (2026): Pacifico Energy sued Hood County, saying it lacked power to deny the project over water.
What we know
- 📍 WhereUnincorporated Hood County, Hood County
- 🏢 CompanyPacifico Energy
- 🌳 Size862 acres
- ⚡ Power it needs100 megawatts (about as much as 80,000 homes)
- 💧 Water20,000 gallons a day
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- What happened in Pacifico's lawsuit against Hood County? 🙋 I'll find out ·
- Has the developer found another water source? 🙋 I'll find out ·
- Is the Fort Spunky site about 560 acres or 862 acres? News reports give different numbers. 🙋 I'll find out ·
What happened so far
- 2026Hood County revoked the Fort Spunky concept plan, 3-2.
- 2026Pacifico Energy sued Hood County, saying it lacked power to deny the project over water.
Local votes and rules
✋ Turned down
Hood County commissioners voted 3-1 to reject a settlement with Sailfish that would have shrunk the Comanche Circle data center from about 2,523 to about 1,375 acres in the county. They then voted unanimously to deny Sailfish's appeal of the county's decision on its on-site permit applications. The developer had warned it could sue.
⚖️ Court case
Two developers, National CRE Holdings LLC and Greenland Capital LLC, sued Hood County, saying their data center campuses (Project Red and Project Yellow) should be approved automatically because the county missed a 30-day deadline. A district judge threw out the case for good, ruling the projects were not 'development plans' under state law. The companies said they would appeal.
✅ Approved
Hood County commissioners voted 3-1 to approve, without conditions, the concept plan for the Comanche Circle data center, a 2,100-acre campus planned by Sailfish near Tolar. The county had given it conditional approval in January 2026. The developer had threatened to sue. Next comes a site plan review covering drainage, water, wastewater and environmental studies.
✋ Turned down
Hood County commissioners voted 3-2 to reject the concept plan for Fort Spunky, a data center and power plant project by Pacifico Energy. The plan lacked key details, such as where its water would come from. Earlier, the Acton Municipal Utility District board voted to deny water service to the project.
📜 Data center rules
Hood County commissioners passed stricter development permit rules for large industrial projects such as AI data centers, crypto mines and power plants. Texas counties cannot zone land, so these rules work through the county's development permit process.
✋ Turned down
Hood County commissioners voted 3-2 against a six-month pause on new large industrial projects, including data centers. During the meeting, a state senator's letter to the Attorney General argued that Texas counties do not have the power to pass such pauses. At least four data centers were proposed in the county. A second try at a pause also failed.
✅ Approved
Hood County commissioners gave conditional approval to the concept plan for the Comanche Circle data center, a 2,100-acre campus that could use up to 3 gigawatts of power.
📌 Other
Hood County commissioners voted 3-1 for a letter of support for 'Project Patriot', which was later revealed to be a data center. The site was later annexed into the City of Granbury.
Drag the slider to compare the land before and now.
Where this comes from
- Eight data centers threaten to transform this small Texas county. Local officials say they have no power to stop them. · The Texas Tribune · June 2, 2026
- Hood County Rejects Data Center Concept Plan · Texas Scorecard · March 10, 2026