๐Ÿ“ฃ Report Something
USA โ€บ Texas โ€บ Hood County โ€บ Unincorporated Hood County
Stopped or cancelled

'Fort Spunky' data center (Pacifico Energy, Hood County)

Also called: Fort Spunky

Pacifico Energy proposed an 862-acre data center called Fort Spunky that would take 100 megawatts from the grid and up to 20,000 gallons of water a day. Hood County first approved its concept plan, but revoked it 3-2 after a local water utility board denied the water request. Pacifico then sued the county.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 6, 2026

Where things stand: County revoked its earlier approval 3-2 after a water utility refused service; the developer sued the county.

๐Ÿ•’ Latest update (2026): Pacifico Energy sued Hood County, saying it lacked power to deny the project over water.

What we know

  • ๐Ÿ“ WhereUnincorporated Hood County, Hood County
  • ๐Ÿข CompanyPacifico Energy
  • ๐ŸŒณ Size862 acres
  • โšก Power it needs100 megawatts (about as much as 80,000 homes)
  • ๐Ÿ’ง Water20,000 gallons a day

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • 2026
    Hood County revoked the Fort Spunky concept plan, 3-2.
  • 2026
    Pacifico Energy sued Hood County, saying it lacked power to deny the project over water.

Local votes and rules

โš–๏ธ Court case

Two developers, National CRE Holdings LLC and Greenland Capital LLC, sued Hood County, saying their data center campuses (Project Red and Project Yellow) should be approved automatically because the county missed a 30-day deadline. A district judge threw out the case for good, ruling the projects were not 'development plans' under state law. The companies said they would appeal.

July 2026

โœ… Approved

Hood County commissioners voted 3-1 to approve, without conditions, the concept plan for the Comanche Circle data center, a 2,100-acre campus planned by Sailfish near Tolar. The county had given it conditional approval in January 2026. The developer had threatened to sue. Next comes a site plan review covering drainage, water, wastewater and environmental studies.

June 9, 2026

โœ‹ Turned down

Hood County commissioners voted 3-2 to reject the concept plan for Fort Spunky, a data center and power plant project by Pacifico Energy. The plan lacked key details, such as where its water would come from. Earlier, the Acton Municipal Utility District board voted to deny water service to the project.

March 2026

๐Ÿ“œ Data center rules

Hood County commissioners passed stricter development permit rules for large industrial projects such as AI data centers, crypto mines and power plants. Texas counties cannot zone land, so these rules work through the county's development permit process.

March 2026

โœ‹ Turned down

Hood County commissioners voted 3-2 against a six-month pause on new large industrial projects, including data centers. During the meeting, a state senator's letter to the Attorney General argued that Texas counties do not have the power to pass such pauses. At least four data centers were proposed in the county. A second try at a pause also failed.

Feb 10, 2026

โœ… Approved

Hood County commissioners gave conditional approval to the concept plan for the Comanche Circle data center, a 2,100-acre campus that could use up to 3 gigawatts of power.

Jan 2026

๐Ÿ“Œ Other

Hood County commissioners voted 3-1 for a letter of support for 'Project Patriot', which was later revealed to be a data center. The site was later annexed into the City of Granbury.

July 2025
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Eight data centers threaten to transform this small Texas county. Local officials say they have no power to stop them. ยท The Texas Tribune ยท June 2, 2026

See something wrong? Tell us and we'll fix it.