USA β€Ί Texas β€Ί Hood County β€Ί Granbury City

No project in Granbury City, but 7 nearby

Who decides here: the City Council of Granbury City votes on zoning. The Hood County may review big projects too.

Nearby (within 15 miles)

Approved, not built yetabout 3 miles away

Sailfish 'Comanche Circle' data center campus (near Tolar)

Unincorporated Hood County, Hood County

2,100 acres

πŸ•’ June 9, 2026: Commissioners Court approved the concept plan without conditions, 3-1.

Stopped or cancelledabout 4 miles away

'Fort Spunky' data center (Pacifico Energy, Hood County)

Unincorporated Hood County, Hood County

862 acres

πŸ•’ 2026: Pacifico Energy sued Hood County, saying it lacked power to deny the project over water.

Reported in the news, not confirmed yet

Built & runningabout 4 miles away

MARA (Marathon) bitcoin mining data center (Granbury area)

Unincorporated Hood County, Hood County

for Marathon (bitcoin mining)

πŸ•’ 2023: Marathon Digital bought the Granbury site from Generate Capital for $178.6 million.

Reported in the news, not confirmed yet

Status unclearabout 4 miles away

'Project Red' and 'Project Yellow' data centers (Hood County)

Unincorporated Hood County, Hood County

677 acres

πŸ•’ July 21, 2026: District Judge Bryan Bufkin dismissed the developers' lawsuit with prejudice.

Approved, not built yetabout 5 miles away

Bilateral Energy 'Project Patriot' power plant and data center campus (Knox Ranch, Granbury)

Granbury, Hood County

2,000 acres

πŸ•’ July 13, 2026: Residents filed petitions to recall the mayor and most council members.

Status unclearabout 8 miles away

Amazon 'Project Spectrum' data center campus (Coates Road, near Comanche Peak)

Unincorporated Hood County, Hood County

1,265 acres Β· for Amazon Web Services

πŸ•’ May 26, 2026: Hood County Commissioners Court accepted the conditional plan, 3-0 (two commissioners ab…

Reported in the news, not confirmed yet

Local votes and rules

πŸ—³οΈ Election

Residents upset about the Project Patriot data center land gathered about 1,450 signatures on petitions to recall the mayor, mayor pro tem and three council members. On July 28, 2026, the city refused to certify them. After residents went to court, the city agreed in late August to present the petitions to council. A September 29 special council meeting ended in a walkout. A recall election could come as early as May 2027.

Sept 29, 2026Source

πŸ—ΊοΈ Zoning change

Granbury City Council rezoned about 2,100 acres of newly annexed land to industrial use, which allows power plants and data centers. The land is linked to the 'Project Patriot' data center idea. Many residents opposed it.

April 7, 2026Source

βš–οΈ Court case

Four residents sued the City of Granbury over the annexation and rezoning of the Project Patriot land. They say city officials broke the Texas Open Meetings Act, including during a group tour of a Bilateral Energy data center in Dallas before the vote, and misled the public about the project's purpose. No ruling had been reported.

April 2026Source

πŸ“Œ Other

Granbury City Council annexed about 2,090 acres of the former Knox Ranch into the city. Residents later learned the land was tied to 'Project Patriot', a possible data center campus with its own power plant linked to Dallas-based Bilateral Energy.

Jan 6, 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Granbury City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Granbury City. Nothing else.

⚑ Your electric company

Depending on where you live in Granbury City: Oncor Electric Delivery Company LLC (company) or Texas-new Mexico Power Co. (company) or United Electric Co-op Service Inc. (co-op (owned by its members)) or Tri-county Electric Co-op, Inc. (co-op (owned by its members)) or City of Granbury (not available).

In much of Texas you can pick who sells you power, but this company owns the power lines.

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.