Send us a tip
USA › Texas › Hood County › Granbury City

1 data center project in Granbury City

Who decides here: the City Council of Granbury City votes on zoning. The Hood County may review big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

In Granbury City

Nearby (within 15 miles)

Approved, not built yetabout 3 miles away

Sailfish 'Comanche Circle' data center campus (near Tolar)

Unincorporated Hood County, Hood County

2,100 acres

🕒 Oct 13, 2026: Hood County Commissioners Court voted 3-1 to reject a settlement with Sailfish. The deal…

Stopped or cancelledabout 4 miles away

'Fort Spunky' data center (Pacifico Energy, Hood County)

Unincorporated Hood County, Hood County

862 acres

🕒 2026: Pacifico Energy sued Hood County, saying it lacked power to deny the project over water.

Reported in the news, not confirmed yet

Status unclearabout 4 miles away

'Project Red' and 'Project Yellow' data centers (Hood County)

Unincorporated Hood County, Hood County

677 acres

🕒 July 21, 2026: District Judge Bryan Bufkin dismissed the developers' lawsuit with prejudice.

Built & runningabout 8 miles away

MARA (Marathon) bitcoin mining data center (Granbury area)

Unincorporated Hood County, Hood County

for Marathon (bitcoin mining)

🕒 Jan 12, 2024: MARA bought the Granbury bitcoin mining site (and one in Nebraska) from Generate Capital…

Reported in the news, not confirmed yet

Status unclearabout 8 miles away

Amazon 'Project Spectrum' data center campus (Coates Road, near Comanche Peak)

Unincorporated Hood County, Hood County

1,265 acres · for Amazon Web Services

🕒 May 26, 2026: Hood County Commissioners Court accepted the conditional plan, 3-0 (two commissioners ab…

Reported in the news, not confirmed yet

Approved, not built yetabout 12 miles away

Amazon data center campus at Comanche Peak nuclear plant (Somervell County)

Unincorporated Somervell County, Somervell County

435 acres · for Amazon Web Services

🕒 Feb 2026: Somervell County Commissioners Court voted to move forward with a development agreement …

Reported in the news, not confirmed yet

Local votes and rules

⚖️ Court case

Granbury's mayor, mayor pro tem and one council member, who are all named in the recall petitions over the Project Patriot data center land, sued the City of Granbury on Oct. 6, 2026. They say the petitions are invalid because of fraud, forgery and other errors, and they want to stop the recall election. These claims have not been proven. On the city attorney's advice, the city stopped scheduling the recall election, which had been planned for May 2027.

Oct 6, 2026Source

🗳️ Election

Residents upset about the Project Patriot data center land gathered about 1,450 signatures on petitions to recall the mayor, mayor pro tem and three council members. On July 28, 2026, the city refused to certify them. After residents went to court, the city agreed in late August to present the petitions to council. A September 29 special council meeting ended in a walkout. A recall election could come as early as May 2027.

Sept 29, 2026Source

🗺️ Zoning change

Granbury City Council rezoned about 2,100 acres of newly annexed land to industrial use, which allows power plants and data centers. The land is linked to the 'Project Patriot' data center idea. Many residents opposed it.

April 7, 2026Source

⚖️ Court case

Four residents sued the City of Granbury over the annexation and rezoning of the Project Patriot land. They say city officials broke the Texas Open Meetings Act, including during a group tour of a Bilateral Energy data center in Dallas before the vote, and misled the public about the project's purpose. No ruling had been reported.

April 2026Source

📌 Other

Granbury City Council annexed about 2,090 acres of the former Knox Ranch into the city. Residents later learned the land was tied to 'Project Patriot', a possible data center campus with its own power plant linked to Dallas-based Bilateral Energy.

Jan 6, 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Granbury City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Granbury City. Nothing else.

⚡ Your electric company

Depending on where you live in Granbury City: Oncor Electric Delivery Company LLC (company) or Texas-new Mexico Power Co. (company) or United Electric Co-op Service Inc. (co-op (owned by its members)) or Tri-county Electric Co-op, Inc. (co-op (owned by its members)) or City of Granbury (not available).

In much of Texas you can pick who sells you power, but this company owns the power lines.

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.

🙋 Open tasks here

  • Who is the data center tenant?
  • How much water will the campus use, and from where?
  • How did the lawsuit over the annexation turn out?
  • Will a recall election be held?

How to help →