2 data center projects in Denton City
Who decides here: the City Council of Denton City votes on zoning. The Denton County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In Denton City
QumulusAI modular data center (Denton)
Denton, Denton County
4 acres
🕒 Jan 13, 2026: City Council approved the permit and a tax break for 8 prefab data center 'pods' on 4 ac…
Reported in the news, not confirmed yet
Being builtCore Scientific / CoreWeave AI data center (Jim Christal Road, Denton)
Denton, Denton County
78.85 acres · for CoreWeave (planned user, per 2024 reports)
🕒 Nov 19, 2024: City Council voted to lease 78.85 acres of city land and approve a new power deal for th…
Nearby (within 15 miles)
Local votes and rules
⏸️ Pause on new data centers
Denton City Council held its second and final public hearing on a 90-day pause on new commercial data center applications and heard the first reading of the ordinance on Oct. 27, 2026. Council took no vote. The vote could come as early as Dec. 1, 2026 and needs 75% of council. Some members talked about extending it to 180 days. The pause would not affect applications already filed, such as the approved Qumulus AI and Core Scientific projects.
📜 Data center rules
Denton's Planning and Zoning Commission voted 5-0 for code changes that would make every new data center get a special use permit approved by City Council. Data centers would be banned in some office and corridor districts, kept 300 feet from homes (now 100 feet), and required to use closed-loop or free-air cooling and file water studies. City Council was set to vote on Oct. 13, 2026. A separate moratorium hearing is set for Oct. 27.
📜 Data center rules
Denton City Council voted 4-0 to change the city's development code. Data centers are now allowed only in light industrial, heavy industrial and public facilities zones, and each one needs a special use permit voted on by council. They must be 300 feet from homes, limit light on neighbors, use closed-loop or free-air cooling, and file water studies. A separate moratorium hearing is set for Oct. 27.
⏸️ Pause on new data centers
Denton City Council voted unanimously to start the legal steps for a 90-day pause on new data centers, which could be extended by 90 more days. Public hearings are set for September 22 and October 27, 2026, and a final vote could come as early as December. Passing it needs three out of four council members. Existing projects, such as Core Scientific's 391-megawatt site, may not be stopped.
What you can do
- Get told first.
We'll email you if anything changes in Denton City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Denton City: Oncor Electric Delivery Company LLC (company) or Texas-new Mexico Power Co. (company) or Wise Electric Co-op Inc. (co-op (owned by its members)) or Tri-county Electric Co-op, Inc. (co-op (owned by its members)) or Denton County Electric Co-op, Inc. (co-op (owned by its members)) or Cooke County Electric Co-op Assn (co-op (owned by its members)) or City of Denton (run by the town).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.
🙋 Open tasks here
- How much water will it use each day?
- Will the city's gas power plant run more to serve it?
- How much water will it use?
- How long does the tax break last?