Project Tomahawk data center (Prosper, withdrawn)

A $580 million data center was proposed on 37 acres in Prosper. After the planning board recommended denial, the developer withdrew, saying it does not want to go where it is not wanted.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled Planning board voted 7-0 to recommend denial Sept. 1, 2026; developer withdrew before the Sept. 8 Town Council vote.

❓ 1 open question about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 7, 2026.

🕒 Latest update (Sept 1, 2026): Prosper Planning and Zoning Commission voted 7-0 to recommend denial.

What we know

  • 📍 WhereNear FM 1385 and Parvin Road, next to a Brazos Electric substation, Prosper, Denton County
  • 🏢 CompanyWhite Rose Partners
  • 🌳 Size37.3 acres
  • 💵 Cost$580 million

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Reports differ on whether the site is in the Denton County or Collin County part of Prosper. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 7, 2026: We checked the site location: approximate location found.

    What happened so far

    • Sept 2026
      White Rose Partners withdrew the project before the Town Council vote.
    • Sept 1, 2026
      Prosper Planning and Zoning Commission voted 7-0 to recommend denial.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Prosper commission recommends denial of $580 million data center · Community Impact · Sept 2, 2026
    2. Project Tomahawk developer scraps plans for Prosper data center · Community Impact · Sept 8, 2026
    3. OpenStreetMap search: FM 1385 at Parvin Road · OpenStreetMap contributors · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.