Send us a tip
Being builtBig (AI-size): 394 megawatts

Core Scientific / CoreWeave AI data center (Jim Christal Road, Denton)

Also called: CoreWeave Denton, Core Scientific Denton

Core Scientific is turning its Denton bitcoin mine into a large AI data center, working with CoreWeave. The city leased it about 79 acres of city land next to the city's gas power plant. The city says it will reach about 394 megawatts by 2027.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Denton City.

Where things stand: Being built City leased land for the expansion in Nov. 2024; full build-out expected in 2027.

❓ 2 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (Nov 19, 2024): City Council voted to lease 78.85 acres of city land and approve a new power deal for the AI expansion.

What we know

  • 📍 Where8171 Jim Christal Road, near the Denton Energy Center, Denton, Denton County
  • 🏢 CompanyCore Scientific
  • 👤 Built forCoreWeave (planned user, per 2024 reports)
  • 🌳 Size78.85 acres
  • ⚡ Power it needs394 megawatts (about as much as 315,200 homes)
  • 🔌 Where the power comes fromCity-owned Denton Municipal Electric; next to the city's gas power plant (Denton Energy Center).
  • 💵 Cost$6.1 billion
  • 👷 Jobs promised300

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will it use each day? 🙋 I'll find out ·
  • Will the city's gas power plant run more to serve it? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 7, 2026: We checked the site location: approximate location found.

    What happened so far

    • Nov 19, 2024
      City Council voted to lease 78.85 acres of city land and approve a new power deal for the AI expansion.

    Local votes and rules

    ⏸️ Pause on new data centers

    Denton City Council held its second and final public hearing on a 90-day pause on new commercial data center applications and heard the first reading of the ordinance on Oct. 27, 2026. Council took no vote. The vote could come as early as Dec. 1, 2026 and needs 75% of council. Some members talked about extending it to 180 days. The pause would not affect applications already filed, such as the approved Qumulus AI and Core Scientific projects.

    Oct 27, 2026

    📜 Data center rules

    Denton's Planning and Zoning Commission voted 5-0 for code changes that would make every new data center get a special use permit approved by City Council. Data centers would be banned in some office and corridor districts, kept 300 feet from homes (now 100 feet), and required to use closed-loop or free-air cooling and file water studies. City Council was set to vote on Oct. 13, 2026. A separate moratorium hearing is set for Oct. 27.

    Oct 13, 2026

    📜 Data center rules

    Denton City Council voted 4-0 to change the city's development code. Data centers are now allowed only in light industrial, heavy industrial and public facilities zones, and each one needs a special use permit voted on by council. They must be 300 feet from homes, limit light on neighbors, use closed-loop or free-air cooling, and file water studies. A separate moratorium hearing is set for Oct. 27.

    Oct 13, 2026

    ⏸️ Pause on new data centers

    Denton City Council voted unanimously to start the legal steps for a 90-day pause on new data centers, which could be extended by 90 more days. Public hearings are set for September 22 and October 27, 2026, and a final vote could come as early as December. Passing it needs three out of four council members. Existing projects, such as Core Scientific's 391-megawatt site, may not be stopped.

    Aug 18, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Data centers rise in Denton · Community Impact · May 7, 2026
    2. $4B bitcoin-to-AI data center project eyed in Denton, Texas · GovTech (Dallas Morning News) · Nov 19, 2024
    3. TDLR TABS TABS2025005706: Core Scientific - Denton, TX, 8171 Jim Christal Road · Texas Department of Licensing and Regulation · Oct 7, 2026
    4. OpenStreetMap search: Jim Christal Road next to the Denton Energy Center · OpenStreetMap contributors · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.