πŸ“£ Report Something
USA β€Ί Texas β€Ί Bastrop County β€Ί Unincorporated Bastrop County

4 data center projects in Unincorporated Bastrop County

Who decides here: the Bastrop County Commissioners Court decides on zoning for land outside city and town limits. Texas counties have very few zoning powers, so land outside cities often has few local rules.

In Unincorporated Bastrop County

Local votes and rules

πŸ“Œ Other

With data center deals under discussion, Bastrop County commissioners updated the county's tax break rules. New projects must invest at least $20 million (or $10 million to expand) and create at least 25 jobs, with a goal of 25% local hires, plus environmental review and benefit standards. A commissioner said tax breaks are the only tool the state gives counties to set conditions.

July 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Unincorporated Bastrop County.
  2. Go to county meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Unincorporated Bastrop County. Nothing else.

⚑ Your electric company

Depending on where you live in Unincorporated Bastrop County: Fayette Electric Co-op, Inc. (co-op (owned by its members)) or Bluebonnet Electric Co-op, Inc. (co-op (owned by its members)).

In much of Texas you can pick who sells you power, but this company owns the power lines.

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.

πŸ™‹ Open tasks here

  • How much power does it use?
  • How much water does it use each day?
  • How many diesel backup generators are on site?
  • How much power and water will it use?
  • Will Bastrop County give a tax break?
  • Who is the tenant?
  • When will plans be filed?
  • How much power and water would it use?
  • Has the state air permit (TCEQ) for the gas plant been approved?
  • Will the project still be built here, or at the company's other possible site in Ohio?
  • How much water will the plant and data center use?

How to help β†’