Being builtBig (AI-size): 112 acres

EdgeConneX Cedar Creek campus 1 (FM 535 and Wolf Lane)

EdgeConneX built a $440 million data center building on 112 acres in Cedar Creek. AI cloud company CoreWeave will use it. More buildings are planned on the campus.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Bastrop County Commissioners Court (for land outside city and town limits).

Where things stand: Being built First building was due to finish in summer 2026; CoreWeave is the tenant.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (May 27, 2026): First 578,000 sq ft building was nearly finished.

What we know

  • 📍 WhereNortheast corner of FM 535 and Wolf Lane, Cedar Creek, Unincorporated Bastrop County, Bastrop County
  • 🏢 CompanyEdgeConneX
  • 👤 Built forCoreWeave
  • 🌳 Size112 acres
  • 💵 Cost$440 million
  • 💸 Tax breaksCounty approved a 10-year, 75% property tax break in Dec. 2024 (passed to CoreWeave in Oct. 2025), plus a 20-year state sales tax exemption on equipment.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 7, 2026: We checked the site location: approximate location found.

    What happened so far

    • Dec 2024
      Bastrop County approved a 10-year, 75% tax break.
    • May 27, 2026
      First 578,000 sq ft building was nearly finished.

    Local votes and rules

    📌 Other

    With data center deals under discussion, Bastrop County commissioners updated the county's tax break rules. New projects must invest at least $20 million (or $10 million to expand) and create at least 25 jobs, with a goal of 25% local hires, plus environmental review and benefit standards. A commissioner said tax breaks are the only tool the state gives counties to set conditions.

    July 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. EdgeConneX expands Bastrop County data center project · Austin American-Statesman · May 28, 2026
    2. AI cloud company CoreWeave to fill $440M Cedar Creek data center · Community Impact · July 24, 2026
    3. Town halls set for 3 Cedar Creek data centers spanning nearly 1,500 acres · Community Impact · June 9, 2026