EdgeConneX Cedar Creek campus 2 (6682 and 6402 FM 535)
EdgeConneX plans a second, much larger campus in Cedar Creek on about 951 acres. The first two buildings cost about $1.4 billion. Seven more buildings could come later.
Where things stand: Construction of two buildings was set to start June 2026 and finish by end of 2028; seven more buildings may follow.
๐ Latest update (June 16, 2026): Town halls held in Elgin, Smithville (June 17) and Bastrop (June 18).
What we know
- ๐ Where6682 and 6402 FM 535, Cedar Creek, Unincorporated Bastrop County, Bastrop County
- ๐ข CompanyEdgeConneX
- ๐ณ Size951 acres
- ๐ต Cost$1.4 billion
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much power and water will it use? ๐ I'll find out
- Will Bastrop County give a tax break? ๐ I'll find out
- Who is the tenant? ๐ I'll find out
What happened so far
- May 28, 2026State filings showed two buildings (about 730,000 sq ft each) on the site.
- June 16, 2026Town halls held in Elgin, Smithville (June 17) and Bastrop (June 18).
Local votes and rules
๐ Other
With data center deals under discussion, Bastrop County commissioners updated the county's tax break rules. New projects must invest at least $20 million (or $10 million to expand) and create at least 25 jobs, with a goal of 25% local hires, plus environmental review and benefit standards. A commissioner said tax breaks are the only tool the state gives counties to set conditions.
Drag the slider to compare the land before and now.
Where this comes from
- EdgeConneX expands Bastrop County data center project ยท Austin American-Statesman ยท May 28, 2026
- Town halls set for 3 Cedar Creek data centers spanning nearly 1,500 acres ยท Community Impact ยท June 9, 2026