2 data center projects in Gregg Township
Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of Gregg Township votes on zoning. The Union County Planning Commission usually reviews big projects too.
In Gregg Township
PNK Group data center (Gregg Township, Union County)
Gregg Township, Union County
for No tenant yet; likely AI
π Sept 14, 2026: Third session of the supervisors' public hearing on PNK P2 LLC's zoning amendment and coβ¦
Stopped or cancelledData Centric LLC data center at Great Stream Commons (canceled)
Gregg Township, Union County
37 acres
π Aug 2025: Union County got an official notice that the company pulled out of the deal.
Reported in the news, not confirmed yet
Nearby (within 15 miles)
Muncy data center (Muncy Township)
Muncy Township, Lycoming County
π Sept 26, 2026: Reports on the 'Danko Data Center' application say the plans include water storage tanksβ¦
Stopped or cancelledabout 13 miles awayTalen Energy data center rezoning (Anthony Township, Montour County)
Anthony Township, Montour County
π Feb 10, 2026: County commissioners unanimously denied Talen's rezoning, saying it gave few details on β¦
Gregg Township Board of Supervisors. We don't know yet if PNK Group data center (Gregg Township, Union County) is on the agenda. Call the office to check before you go.
Local votes and rules
βΈοΈ Pause on new data centers
Gregg Township supervisors voted unanimously to pause new data center applications for up to 180 days. A data center plan already filed for Great Stream Commons is not covered by the pause.
πΊοΈ Zoning change
PNK P2 LLC asked Gregg Township (Union County) to change its zoning to add data centers and to approve a data center as a conditional use at 198 Enterprise Blvd. in the Great Stream Commons park near Allenwood. The plan reuses part of a large warehouse. Hearings began July 20, 2026 and continued August 25 and September 14. No decision was found.
What you can do
- Get told first.
We'll email you if anything changes in Gregg Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.
π Open tasks here
- When is the conditional use hearing?
- How much power will it use?
- How many buildings could be added later?
- Is Data Centric or KSR Capital looking at other Pennsylvania sites (DEP lists a KSR project in Plains Township)?