Muncy data center (Muncy Township)

Also called: Danko Holdings II, Fishlips LLC, The Liberty Group

Danko Holdings II and Fishlips LLC want to build a data center complex along Yetter Road in Muncy Township. The developer says the plan was automatically approved because the township missed a deadline. The township and neighbors are fighting that claim.

βœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Developer filed for conditional use in April 2026, then claimed in July 2026 that the plan was 'deemed approved' because the township missed a hearing deadline. The township disputes this, and neighbors appealed.

πŸ•’ Latest update (Sept 26, 2026): Reports on the 'Danko Data Center' application say the plans include water storage tanks and an on-site water treatment facility. The amount of water was not stated.

What we know

  • πŸ“ WhereAlong Yetter Road, Muncy Township, Lycoming County
  • 🏒 CompanyDanko Holdings II LP and Fishlips LLC (The Liberty Group)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

πŸ”Ž What we checked

  • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

What happened so far

  • April 28, 2026
    Developer filed a conditional use application for a data center complex.
  • July 2026
    Developer published a legal notice claiming 'deemed approval' because no hearing was held within 60 days; the township solicitor said the township would challenge it.
  • Sept 26, 2026
    Reports on the 'Danko Data Center' application say the plans include water storage tanks and an on-site water treatment facility. The amount of water was not stated.

Local votes and rules

βš–οΈ Court case

An environmental group, local residents, and Muncy Township itself filed an appeal in Commonwealth Court against the automatic approval of the Muncy data center. They argue the approval violates residents' rights under the state constitution.

Sept 25, 2026

βœ… Approved

The developer said its Muncy data center plan was automatically approved because the township did not hold a hearing within 60 days, as state law requires. The township disputes this and says the developer skipped a required first step.

July 2026

⏸️ Pause on new data centers

Muncy Township put a pause of up to nine months on data centers because it had no zoning rules for them. The township will not process data center permits or plans until rules are adopted or the pause ends.

May 1, 2026
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

2018–20202021–2023
We only know the town, so this shows the town center, not the exact site. Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Muncy data center developers move to quash neighbors' appeal Β· NorthcentralPA.com
  2. Muncy Data Center (Danko Holdings II / Fishlips, Muncy Township) Β· More Than Just Parks Data Center Tracker
  3. Palmerton discusses data center Β· Times News (tnonline.com) Β· Sept 26, 2026
  4. Water Use by Data Centers in the Susquehanna River Basin - FAQ Β· Susquehanna River Basin Commission Β· 2026
  5. Water Application and Approval Viewer (WAAV) Β· Susquehanna River Basin Commission Β· Oct 6, 2026