1 data center project in Muncy Township
Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of Muncy Township votes on zoning. The Lycoming County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
PNK Group data center (Gregg Township, Union County)
Gregg Township, Union County
for No tenant yet; likely AI
🕒 Oct 27, 2026: Gregg Township supervisors voted 3-0 to grant PNK P2 LLC conditional use approval for Ph…
Stopped or cancelledabout 11 miles awayTalen Energy data center rezoning (Anthony Township, Montour County)
Anthony Township, Montour County
870 acres
🕒 Feb 10, 2026: County commissioners unanimously denied Talen's rezoning, saying it gave few details on …
Stopped or cancelledabout 12 miles awayData Centric LLC data center at Great Stream Commons (canceled)
Gregg Township, Union County
37 acres
🕒 Aug 2025: Union County got an official notice that the company pulled out of the deal.
Reported in the news, not confirmed yet
Muncy Township Board of Supervisors. We don't know yet if Muncy data center (Muncy Township) is on the agenda. Call the office to check before you go.
Local votes and rules
📜 Data center rules
Muncy Township will hold a public hearing on Nov. 4, 2026 at 7 p.m. at the Township Building on its draft 20-page data center ordinance. Adoption is planned for December.
📜 Data center rules
Muncy Township held its public hearing on its draft data center ordinance in early November 2026. The draft allows fines of $1,000 a day. Residents asked for stronger rules, and one family presented a stricter version. No vote was taken; supervisors are expected to vote on Dec. 9, 2026.
⚖️ Court case
An environmental group, local residents, and Muncy Township itself filed an appeal in Commonwealth Court against the automatic approval of the Muncy data center. They argue the approval violates residents' rights under the state constitution.
✅ Approved
The developer said its Muncy data center plan was automatically approved because the township did not hold a hearing within 60 days, as state law requires. The township disputes this and says the developer skipped a required first step.
⏸️ Pause on new data centers
Muncy Township put a pause of up to nine months on data centers because it had no zoning rules for them. The township will not process data center permits or plans until rules are adopted or the pause ends.
📌 Other · Lycoming County
Lycoming County started a curative amendment for data centers in the towns that use county zoning. This legal step gives towns up to 180 days to write data center rules while blocking competing challenges from landowners. About 20 communities had joined it by June 2026.
What you can do
- Get told first.
We'll email you if anything changes in Muncy Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.
🙋 Open tasks here
- What exactly was approved and when?
- How much power and water would it use?
- What did the court decide on the neighbors' appeal?
- What did the Lycoming County court decide on the developer's request (motion to quash) to throw out the neighbors' appeal of the deemed approval? A hearing was set for Nov. 6, 2026.