PNK Group data center (Gregg Township, Union County)
Also called: 198 Enterprise Boulevard
PNK Group wants to turn part of an existing 478,000-square-foot building at Great Stream Commons in Gregg Township into a data center. Township supervisors gave conditional use approval on Oct. 27, 2026, with conditions on noise, water and decommissioning. It still needs land development approval and permits, and Union County turned down its substation.
What happens next?
🗓️ Next meeting of the people who decide: Monday, December 7, 2026, 4:30 PM Eastern Time (local time)
Gregg Township Board of Supervisors meeting
📍 Regular monthly meeting. Check the township website for the place.
Regular meeting. PNK's curative amendment deadline was extended to Dec. 14, 2026.
The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.
🗓️ Vote: Monday, December 14, 2026 (time not announced)
Deadline for Gregg Township to act on PNK's curative amendment (extended by agreement).
How: Watch the township website for a meeting notice.
👥 Reported, not confirmed yetSourceNot live: please check with the office first.
🗓️ No meeting or deadline known yet.
Where things stand: Approved, not built yet Supervisors voted 3-0 on Oct. 27, 2026 to grant conditional use approval with 31 conditions. Land development review and permits come next.
- Nov 2, 2026: Our records now list PNK Group data center (Gregg Township, Union County) as approved Source
❓ 5 open questions about it: see below.
Last checked Nov 2, 2026.
🕒 Latest update (Oct 27, 2026): Gregg Township supervisors voted 3-0 to grant PNK P2 LLC conditional use approval for Phase 1, about 252,000 square feet inside the existing building at 198 Enterprise Boulevard. The 31 conditions include noise studies, closed-loop cooling with no well or stream water, an emergency plan, and a decommissioning bond. PNK said it moved about 40 backup generators indoors and moved the substation farther from homes.
What we know
- 📍 Where198 Enterprise Blvd., Allenwood (Commercial Manufacturing district); existing 478,000 sq ft building, Gregg Township, Union County
- 🏢 CompanyPNK P2 LLC (PNK Group, New York)
- 👤 Built forNo tenant yet; likely AI
- 🗼 New power linesYes
- ❄️ CoolingClosed-loop cooling (developer claim)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much power will it use? 🙋 I'll find out ·
- How many buildings could be added later? 🙋 I'll find out ·
- How much will PPL's new Allenwood power line cost, and will any of that cost reach other PPL customers' bills? 🙋 I'll find out ·
- Has Gregg Township posted its written decision with the 31 conditions for PNK's data center? 🙋 I'll find out ·
- What will the community benefits agreement between PNK and Gregg Township say, and will it be public? 🙋 I'll find out ·
🔎 What we checked
- Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.
What happened so far
- April 2026PNK held an open house; many neighbors opposed.
- Sept 14, 2026Third session of the supervisors' public hearing on PNK P2 LLC's zoning amendment and conditional use requests, at the Warrior Run Fire Dept. Social Hall.
- Oct 2026PPL Electric Utilities published a fact sheet for a new 230 kV power line, about 6.8 miles long, from the Elimsport Substation to a new data center customer near US Route 15. Poles would average about 140 feet tall. Construction would run from late 2027 to the end of 2029, pending approval. The Sun-Gazette reported the line is for PNK's project and that PNK will pay its costs.
- Oct 2026PNK and the township agreed to extend the deadline to act on PNK's curative amendment to Dec. 14, 2026.
- Oct 6, 2026Union County commissioners turned down PNK's application for an electrical substation at Great Stream Commons, saying it lacked information. They want it reviewed with the whole project.
- Oct 21, 2026Union County sent PNK a cease-and-desist letter saying substation work started without the needed approvals. PNK has 30 days to confirm in writing that work other than safety work has stopped. PNK says the substation serves the whole industrial park.
- Oct 27, 2026Gregg Township supervisors voted 3-0 to grant PNK P2 LLC conditional use approval for Phase 1, about 252,000 square feet inside the existing building at 198 Enterprise Boulevard. The 31 conditions include noise studies, closed-loop cooling with no well or stream water, an emergency plan, and a decommissioning bond. PNK said it moved about 40 backup generators indoors and moved the substation farther from homes.
Local votes and rules
⏸️ Pause on new data centers
Gregg Township supervisors voted unanimously to pause new data center applications for up to 180 days. A data center plan already filed for Great Stream Commons is not covered by the pause.
🗺️ Zoning change
PNK P2 LLC asked Gregg Township (Union County) to change its zoning to add data centers and to approve a data center as a conditional use at 198 Enterprise Blvd. in the Great Stream Commons park near Allenwood. The plan reuses part of a large warehouse. Hearings began July 20, 2026 and continued August 25 and September 14. No decision was found.
Drag the slider to compare the land before and now.
Where this comes from
- Possibility of data centers in central PA sparks public pushback · WITF / WPSU · July 4, 2026
- Supervisors Meeting (township calendar) · Gregg Township · Oct 6, 2026
- Public notice - 2nd continuation, PNK data center hearing · Gregg Township · Aug 2026
- Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
- Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026
- OpenStreetMap map check · OpenStreetMap contributors · Oct 7, 2026
- News & Notices: Special Meeting Oct. 27, 2026 (PNK P2 LLC conditional use decision) · Gregg Township · Oct 2026
- Gregg Township to vote on data center proposal Oct. 27 · The Daily Item · Oct 19, 2026
- Allenwood 230kV Transmission Project fact sheet · PPL Electric Utilities · Oct 2026
- More details for Allenwood data center proposal surface · Williamsport Sun-Gazette · Oct 23, 2026
- Union County investigates possible site violations from PNK Group · The Daily Item · Oct 14, 2026
- PA: Gregg Township Supervisors Grant Conditional Approval for Data Center Following Public Review · Trade & Industry Development · Oct 30, 2026