1 data center project in Olyphant Borough
Who decides here: the Borough Council of Olyphant Borough votes on zoning. The Lackawanna County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Sunnyside Road data center (Jessup)
Jessup, Lackawanna County
🕒 Sept 25, 2026: News reports said the Sunnyside Road project is 'tied up in litigation' after Council's …
Proposedabout 2 miles awayBreaker Street data center campus (Jessup)
Jessup, Lackawanna County
131 acres
🕒 Sept 25, 2026: News reports said Breaker Street Associates LLC, tied to Catalyst Commercial Development…
Proposedabout 3 miles awayDBT-Data Lackawanna One (Jessup)
Jessup, Lackawanna County
39 acres
🕒 Sept 4, 2026: Application filed for a 200,000-square-foot, one-story data center.
Reported in the news, not confirmed yet
Stopped or cancelledabout 3 miles awayBlakely data center campus
Blakely, Lackawanna County
209 acres
🕒 Sept 12, 2025: Developers withdrew the zoning change request after the borough declined another public …
Proposedabout 3 miles awayDickson City Development data center (Bell Mountain)
Dickson City, Lackawanna County
🕒 Sept 18, 2026: The Times-Tribune listed the Bell Mountain project (4 buildings) as denied by the zoning…
Stopped or cancelledabout 4 miles awayWildcat Ridge data center campus (Archbald)
Archbald, Lackawanna County
574 acres
🕒 Oct 30, 2026: A lawyer for the developer, Cornell Realty Management, sent a legal notice to a county c…
Status unclearabout 5 miles awayDBT-Data Lackawanna Two, Three and Four sites (Archbald/Jessup)
Archbald, Lackawanna County
355 acres
🕒 Sept 2026: Reported that DBT holds memorandums with SLIBCO for three more sites.
Reported in the news, not confirmed yet
Local votes and rules
🤝 Agreement with the company
Olyphant officials proposed settling ERCOR Triboro's lawsuit with a $101 million, 15-year community benefits agreement for seven data centers on about 471 acres. A special vote set for Nov. 5, 2026 was cancelled after a neighboring landowner said it would ask to join the court case. No new vote date has been reported.
📌 Other · Lackawanna County
Lackawanna County commissioners voted unanimously to hire EmPower Analytics Group for $165,000. Over 90 days the firm will study the pollution and health effects of more than a dozen proposed data center campuses and power plants in the county.
🤝 Agreement with the company
Olyphant Borough Council voted 6-0 to settle a lawsuit by Triboro Commerce Park. The settlement confirms the borough's April 2026 data center zoning is in effect. Data centers are a conditional use on about 1,000 acres of industrial land and must buy power from the borough's own electric company. The vote did not approve any project.
What you can do
- Get told first.
We'll email you if anything changes in Olyphant Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Olyphant Borough: PPL Electric Utilities Corp. (company) or Borough of Olyphant (not available).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.
🙋 Open tasks here
- Will a data center application be filed?
- How much water and power would 'Project Triboro' need?
- Has Ercor Triboro filed a conditional use application, and when is the hearing?
- Reports have said both 12 and nine data centers. How many are actually planned?
- Will Olyphant Borough Council vote on the proposed settlement and $101 million community benefits agreement with ERCOR Triboro, and when?