1 data center project in Dickson City Borough
Who decides here: the Borough Council of Dickson City Borough votes on zoning. The Lackawanna County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In Dickson City Borough
Nearby (within 15 miles)
Blakely data center campus
Blakely, Lackawanna County
209 acres
🕒 Sept 12, 2025: Developers withdrew the zoning change request after the borough declined another public …
Stopped or cancelledabout 3 miles awayWildcat Ridge data center campus (Archbald)
Archbald, Lackawanna County
574 acres
🕒 Oct 30, 2026: A lawyer for the developer, Cornell Realty Management, sent a legal notice to a county c…
Status unclearabout 3 miles awayTriboro data center site (Olyphant)
Olyphant, Lackawanna County
471 acres
🕒 Nov 4, 2026: Olyphant cancelled the Nov. 5 special meeting after the borough's lawyer said a neighbor…
Proposedabout 4 miles awayScranton Materials data center campus (Ransom Township)
Ransom Township, Lackawanna County
251 acres
🕒 Sept 3, 2026: News reports said the developer's second lawsuit (asking a judge to rule on the zoning) …
Proposedabout 4 miles awayBreaker Street data center campus (Jessup)
Jessup, Lackawanna County
131 acres
🕒 Sept 25, 2026: News reports said Breaker Street Associates LLC, tied to Catalyst Commercial Development…
Approved, not built yetabout 4 miles awaySunnyside Road data center (Jessup)
Jessup, Lackawanna County
🕒 Sept 25, 2026: News reports said the Sunnyside Road project is 'tied up in litigation' after Council's …
Local votes and rules
📌 Other · Lackawanna County
Lackawanna County commissioners voted unanimously to hire EmPower Analytics Group for $165,000. Over 90 days the firm will study the pollution and health effects of more than a dozen proposed data center campuses and power plants in the county.
✋ Turned down
Dickson City's Zoning Hearing Board unanimously rejected a developer's challenge to the borough's data center rules. The developer argued the manufacturing zone lacks power lines and space. The fight now moves to county court.
⚖️ Court case
The developer Dickson City Development LLC asked the county court to cancel Dickson City's new data center zoning law. The company calls the rules exclusionary because they block its Bell Mountain project.
📜 Data center rules
Dickson City Borough Council voted unanimously to allow data centers only in its light manufacturing (M1) zone, and only with a special exception from the zoning board. Data centers are not allowed in homes or open-space zones. This came after a developer proposed a big campus on Bell Mountain.
What you can do
- Get told first.
We'll email you if anything changes in Dickson City Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.
🙋 Open tasks here
- How much power would it use?
- What will the county court decide?
- Who is the end user?