1 data center project in Clifton Township

Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of Clifton Township votes on zoning. The Lackawanna County Planning Commission usually reviews big projects too.

In Clifton Township

Nearby (within 15 miles)

πŸ—“οΈ Public meeting: Oct 15, 2026 Β· 7:00 PM
Clifton Township Board of Supervisors. Anyone can come and speak.
Regular monthly meeting; new data center ordinance has been on recent agendas.
πŸ“ Supervisors meet the third Thursday of each month at 7 p.m. (work session 6:30 p.m.). The Sept. 17 hearing on the new data center ordinance was at the Gouldsboro Fire Hall, 490 Main Street, Gouldsboro; the township office is at 361 State Route 435. Check cliftontownship.com for the October location.

Local votes and rules

πŸ“Œ Other Β· Lackawanna County

Lackawanna County commissioners voted unanimously to hire EmPower Analytics Group for $165,000. Over 90 days the firm will study the pollution and health effects of more than a dozen proposed data center campuses and power plants in the county.

Sept 2026Source

βš–οΈ Court case

A Lackawanna County judge voided Clifton Township's data center zoning after challenges from the Project Gold developer. The township is now working on new data center rules.

Aug 20, 2026Source

πŸ“œ Data center rules

After the court ruling, Clifton Township is drafting new data center rules. The draft includes a 100-foot buffer, a limit that kicks in for heavy water use, and a plan for removing buildings when a data center closes. Residents asked for bigger buffers and a 35-foot height limit.

Aug 2026Source

🀝 Agreement with the company

Clifton Township supervisors unanimously approved a legal settlement with the Project Gold developer. It allows five two-story data center buildings on three sites along Route 380. More than 100 residents came to oppose it, and some promised to sue.

Jan 2026Source

βš–οΈ Court case

The Project Gold developer, 1778 Rich Pike LLC, appealed the zoning board's ruling to county court. It argued the township's rules really did block data centers. In August 2026 a county judge voided the township's data center zoning.

Nov 26, 2025Source

πŸ“Œ Other

Clifton Township's zoning board unanimously ruled that the township's data center rules were legal and did not unfairly shut out data centers. This rejected a challenge from the Project Gold developer.

Nov 19, 2025Source

βœ‹ Turned down

Clifton Township supervisors voted 2-1 against a legal settlement with the developer of Project Gold, a planned campus of about 30 data center buildings. The deal would have allowed two data center buildings in residential areas.

Sept 29, 2025Source

πŸ“œ Data center rules

Clifton Township supervisors adopted data center zoning rules after a developer claimed the township's zoning left no room for data centers. The developer said the new rules were too strict. A county judge voided the township's data center zoning in August 2026.

May 2025Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Clifton Township.
  2. Go to township meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Clifton Township. Nothing else.

⚑ Your electric company

PPL Electric Utilities Corp. (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.

πŸ™‹ Open tasks here

  • How many megawatts will the campus use in total?
  • Who is the end user?
  • Will new high-voltage power lines be needed?
  • What happened to the Covington Township part of the plan?
  • What is the status of residents' challenge to the settlement?

How to help β†’