Send us a tip
Status unclear

Plains Township data center site (KSR)

Also called: Unnamed Data Center (KSR), Energy and Technology Overlay District

Pennsylvania's environmental agency lists a possible data center by a company called KSR in Plains Township. Township leaders say no one has applied yet, but they are writing a zoning overlay of about 592 acres where data centers could go. Land purchases in the area have worried residents.

👥 Reported, not confirmed yetSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Plains Township.

Where things stand: Status unclear DEP lists a KSR data center here, but township officials said in September 2026 that no one has applied. The township is writing a 592-acre data center overlay.

  • Oct 22, 2026: Plains Township, Luzerne County: zoning change decided Source

❓ 3 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (Sept 22, 2026): Packed hearing on a 592-acre Energy and Technology Overlay District. Land purchases in the area have led to rumors of a data center.

What we know

  • 📍 WhereNear Interstate 476, across from where Westminster and Jumper roads meet Old Pittston Boulevard (proposed overlay area), Plains Township, Luzerne County
  • 🏢 CompanyKSR (per DEP list)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is KSR, and what land has it bought in Plains Township? 🙋 I'll find out ·
  • When will commissioners vote on the overlay district? 🙋 I'll find out ·
  • Is this linked to the KSR Capital-backed company that dropped the Great Stream Commons deal? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • April 2026
      Township commissioners started a curative amendment, pausing new proposals for six months while they write data center rules.
    • Sept 22, 2026
      Packed hearing on a 592-acre Energy and Technology Overlay District. Land purchases in the area have led to rumors of a data center.

    Local votes and rules

    🗺️ Zoning change

    Plains Township commissioners dropped a plan for a 'technology and energy' overlay district that would have allowed data centers on conservation land near the Turnpike. They will write new rules that allow data centers only by conditional use in the existing industrial zone. A hearing on that will be set later.

    Oct 22, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Plains Twp. holds hearing on data-center overlay · Citizens' Voice · Sept 23, 2026
    2. 'This isn't something we've ever taken lightly': Plains Twp. weighs data center zoning · Times Leader · Sept 22, 2026
    3. PA Data Center Permit Tracker - all projects list (CSV behind the DEP map) · Pennsylvania Department of Environmental Protection · Oct 6, 2026

    See something wrong? Tell us and we'll fix it.