ProposedBig (AI-size): 520 acres

Pennsylvania Glacial Till data center overlay (Tobyhanna Township)

Tobyhanna Township created a data center overlay district along Caughbaugh Road that would benefit Pennsylvania Glacial Till LLC. Neighbors say it is illegal spot zoning and are challenging it.

👥 Reported, not confirmed yetSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Tobyhanna Township.

Where things stand: Proposed Residents challenged the township's data center overlay ordinance (No. 5-80) before the Zoning Hearing Board in April 2026.

❓ 3 open questions about it: see below.

Last checked Nov 9, 2026.

🕒 Latest update (April 16, 2026): Zoning Hearing Board continued a hearing on residents' challenge that the overlay is illegal spot zoning.

What we know

  • 📍 WhereCaughbaugh Road at Route 115, Tobyhanna Township, Monroe County
  • 🏢 CompanyPennsylvania Glacial Till LLC
  • 🌳 Size520 acres
  • ❄️ CoolingClosed-loop water system required by the overlay (no public water there)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • What did the Zoning Hearing Board decide? 🙋 I'll find out ·
  • Who is the data center developer and end user? 🙋 I'll find out ·
  • How many buildings and megawatts are planned on the 520-acre Glacial Till site? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 6, 2026: We checked the Delaware River Basin Commission's (DRBC) list of pending applications (August 2026): there is no application for this data center. DRBC said in November 2025 it had not received any data center applications. A data center needs its own DRBC approval only if it takes more than 100,000 gallons a day from its own wells or streams, or discharges more than 50,000 gallons a day (lower limits in some protected areas). Buying water from a water company does not need a separate DRBC approval.

    What happened so far

    • Dec 15, 2025
      Supervisors approved a data center overlay for the 520-acre Pennsylvania Glacial Till property on Caughbaugh Road, next to the Lehigh River. It is zoned rural residential, has active mining, wetlands and conservation land around it. Rules include a closed-loop water system, a 70-decibel noise limit with sound studies before and after building, a minimum lot size and large setbacks.
    • April 16, 2026
      Zoning Hearing Board continued a hearing on residents' challenge that the overlay is illegal spot zoning.

    Local votes and rules

    ⚖️ Court case

    Residents and the Stoddartsville Association challenged Ordinance 580 before the Tobyhanna Township Zoning Hearing Board. They say it is illegal spot zoning that helps a single landowner and goes against the purpose of the rural residential district. Hearings ran from March to at least June 22, 2026.

    March 11, 2026

    🗺️ Zoning change

    Tobyhanna Township passed Ordinance 580, which creates a data center overlay district and allows data centers there. The overlay covers about 520 acres of rural residential land tied to one developer, Pennsylvania Glacial Till LLC.

    Dec 15, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Tobyhanna Twp. public hearing draws crowd as residents challenge zoning ordinance · FOX56 · April 17, 2026
    2. Tobyhanna Township approves second data center zoning overlay · FOX56 WOLF · Dec 16, 2025
    3. Board of Supervisors 2026 (meeting schedule) · Tobyhanna Township · Oct 6, 2026
    4. Public Notice (Zoning Hearing Board, June 22, 2026) · Tobyhanna Township · June 2026
    5. Tobyhanna Draft Data Center Overlay map (prepared by Monroe County Planning Commission) · Tobyhanna Township / Monroe County Planning Commission · Oct 24, 2025
    6. Frequently Asked Questions: Data Centers · Delaware River Basin Commission · Nov 24, 2025
    7. DRBC Project Review: Pending Project Status (August 2026) · Delaware River Basin Commission · Aug 2026