USA › Pennsylvania › Beaver County › Big Beaver Borough

1 data center project in Big Beaver Borough

Who decides here: the Borough Council of Big Beaver Borough votes on zoning. The Beaver County Planning Commission usually reviews big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

In Big Beaver Borough

Nearby (within 15 miles)

Local votes and rules

🗺️ Zoning change

Big Beaver council passed Ordinance 245, changing zoning so data centers are allowed in a commercial district. Switch has since proposed a data center campus at the former Pittsburgh International Race Complex, drawing a crowd of about 100 opponents in June 2026.

Sept 16, 2025Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Big Beaver Borough.
  2. Go to borough meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Big Beaver Borough. Nothing else.

⚡ Your electric company

FirstEnergy Pennsylvania (formerly Penn Power) (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.

🙋 Open tasks here

  • When will the Big Beaver planning commission and borough council vote on the land development plan?
  • How much electricity will the campus use?
  • Where will water come from, and could it affect private wells nearby?
  • How many diesel generators make up the 270 megawatts of backup power, and how often will they be tested?
  • Who is the tenant?
  • Did the borough sign an agreement to keep the plans private (NDA)?
  • Will Switch ask for a tax break?
  • How much water will Switch need to fill its closed-loop cooling system at the start, and which water authority will supply it?
  • What is the new deadline for Big Beaver Borough to act on Switch's land development plan?
  • What did the Big Beaver planning commission recommend on Oct. 22, 2026, and when will Borough Council vote on Switch's plan?