Built & runningBig (AI-size): 120 megawatts

Mawson / Big Digital Energy bitcoin mine and AI site (Midland)

Also called: Big Digital Energy Midland, Mawson Infrastructure Group Midland

A company now called Big Digital Energy runs a large bitcoin mining site of about 120 megawatts in Midland. It has signed a deal to host computer chips for an AI customer, with talk of growing to 144 megawatts. This is separate from the Fezzik Energy data center proposal in Midland.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

Where things stand: Built & running Running bitcoin mining and hosting site (about 120 MW). The company signed a 20 MW AI customer deal with a possible expansion to 144 MW.

❓ 3 open questions about it: see below.

📣 Report noise, water or power bill changes

Last checked Oct 7, 2026.

What we know

  • 📍 Where950 10th Street, on former steel mill land, Midland, Beaver County
  • 🏢 CompanyMawson Infrastructure Group (now Big Digital Energy)
  • 👤 Built forBitcoin mining and hosting customers; an unnamed AI customer
  • ⚡ Power it needs120 megawatts (about as much as 96,000 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much of the Midland site is moving from bitcoin mining to AI? 🙋 I'll find out ·
  • How much water and power does it use, and from where? 🙋 I'll find out ·
  • Does the borough have noise limits for the site? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    Local votes and rules

    🗺️ Zoning change

    Residents packed a Midland council meeting over a proposed zoning change that would let Fezzik Energy build a data center at a former steel mill site. Council sent the request to the borough and county planning commissions and set a public hearing for September 10.

    2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Mawson Infrastructure Group signs 20MW lease with AI customer · Data Center Dynamics
    2. U.S. Data Centers (FracTracker Alliance data, entry 'Big Digital Energy Midland') · FracTracker Alliance · Aug 5, 2026
    3. Big Digital Energy: Midland, PA · Baxtel · Oct 7, 2026
    4. U.S. Census Geocoder result for 950 Railroad Ave, Midland, PA 15059 · U.S. Census Bureau · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.